Progress Review Meeting<br />

Page 4<br />

* Draft in place to be walked down today. (8/24)<br />

IV.<br />

UPDATED ROLLING 3-4 WEEK LOOK AHEAD SCHEDULE<br />

o See attached.<br />

V. WEEKLY PRODUCTION TABLE<br />

* No intrusive work can be started relative to Trench I until the PSR has been approved and signed<br />

off by WCH management.<br />

* None provided.<br />

VI.<br />

VII.<br />

VIII.<br />

IX.<br />

MANPOWER<br />

* See attached.<br />

* WCH asks if DDI has any plans to bring on an additional teamster. (8/10) DDI indicated there<br />

are no plans to bring on another teamster. This leaves seven (7) teamsters for 10 trucks. (8/17)<br />

* Recently WCH observed operators driving water trucks. Per the HSSA contract that is not<br />

allowable. DDI will issue a letter to their sub-tier, WCI concerning this. (8/10) DDI has not yet<br />

issued letter. (8/17) No update. (8/24)<br />

EQUIPMENT<br />

* See attached.<br />

* 350 excavator will be on site by the end of the week. A bucket that may be utilized on this<br />

machine that is configured for CRATER use is coming from the WCH 100-D project without<br />

required escorting, etc. (8/3) No update, DDI to confirm the ETA of the 350 to the project.<br />

(8/10) The 350 excavator will be on site by the end of the week or first of next week. (8/17)<br />

* The 225 excavator will be moved to allow for decontamination and will eventually be moved off<br />

site. (8/24)<br />

WORK PACKAGE NEEDS IN ORDER OF PRIORITY AS SET BY DDI<br />

* None.<br />

* WCH intends to begin working on Trench I silo work packages in early August. Tentative<br />

meeting set for 8/16 to discuss work package for Trench I silos. WCH to confirm with planners<br />

on schedule. (8/3) When the initial work package is developed, craft will be involved in the fine<br />

tuning of the WP. (8/10) Meeting postponed to Monday, 8/23. (8/17) Meeting moved to<br />

Wednesday 8/25 at 8:00. In the near future a WCH planner will be on site three days a week for<br />

support with work packages and technical procedure needs. (8/24)<br />

MATERIAL<br />

*DDI is planning to begin the process of ordering ecology blocks that will be used in the Trench I<br />

Silo remediation. (7/27) DDI is planning for approximately 150 ecology blocks. (8/3)<br />

0 WCH will be issuing an additional change notice for trench I that will require provision of<br />

means and methods as well as materials such as ecology blocks. (8/10)<br />

X. QUALITY<br />

*The Kenworth haul trucks are on hold for use with 25-ton cans until final certification data is<br />

provided. Submittal for certification was returned status 3. No update (5/4). No update. (5/11)<br />

No update. (5/18) No update. (6/1) No update. (6/8)<br />

o WCH issued SDR (FR-2010-IF-0092-017) to DDI on 5/24/2010 for shuttle truck<br />

specifications. (5/25) No update. (6/1) No update. (6/8) DDI to provide CAR by 6/24/20 10.