Progress Review Meeting<br />

Page 3<br />

* Trench "I" planning and discussions are underway. DDI has not yet received any feedback from<br />

Rowand regarding bucket dimensions, spec sheet, cameras, etc. DDI to provide this information<br />

by Monday, 3/18/2010. The Jewel rep was on site this week and is going to provide additional<br />

information to answer the questions raised. DDI needs to provide a large number of ecology<br />

blocks for use in Trench 1. These need to have a rated picking point and be in very good shape.<br />

DDI to follow-up with Jewell and Rowand machinery for information on cameras and<br />

dimensional information on clam shell. DNFS13 presentation went well. WCH is planning a<br />

management review at the end of next week. WCH needs additional information on the camera<br />

and other equipment as soon as possible.<br />

* Discussed the utilization of Doug Bowers on SCBA. It is expected that this is a DDI function.<br />

Explained that DDI is to provide equipment for these types of entries. But, with that said, WCH<br />

will do everything it can to support these tasks as necessary. DDI is getting a person SCBA<br />

certified. A discussion regarding the use of WCH equipment by trained personnel is needed.<br />

* DDI is to identify and establish a container dumping area. This will be coordinated with the<br />

WCH EPL. Identifying this area needs to become a priority. The can in the HRA has been there<br />

a while and needs to be addressed.<br />

* WCH has three confirmatory sampling sites what will require DDI equipment support. More<br />

informnation will be provided soon. WCH pushing for an April timeframe to perform this work.<br />

* WCH is concerned that DDI has not produced a baseline schedule for the project. DDL planning<br />

to submit next revision of baseline schedule on 3/16/2010. WCH will be issuing an SDR to DDI<br />

for the lack of a baseline schedule. WCH has received submittal and is in review.<br />

a DDI to develop a process for segregating metal debris from void space to keep the wrong items<br />

from being loaded out. DDI is developing a posting system to identify specific segregated areas.<br />

DDI is working on this, nothing has been implemented to date.<br />

III.<br />

IV.<br />

PROJECT DESIGN DRAWINGS<br />

*WCH return electrical and traffic control drawings to DDI, status 2. DDI will be resubmitting<br />

soon incorporating the WCH comments. DDI to submit this week.<br />

UPDATED ROLLING 3-4 WEEK LOOK AHEAD SCHEDULE<br />

* See attached.<br />

* DDI Project Manager has given resignation, last day is Thursday, 3/25/20 10. Discussion of no<br />

field work activities potential on Monday 4/1/2010 without the PM Key Person onsite.<br />

V. WEEKLY PRODUCTION TABLE<br />

0 See attached.<br />

VI.<br />

VII.<br />

MANPOWER<br />

* Several resumes for Samplers have been received by DDI, DDI is evaluating potential candidates.<br />

0 Discussed scheduling difficulties for physicals at AMH. Mr. Heard spoke with the WCH OH<br />

department that schedules AMH physicals. If a teamster has a current DOT physical, they can<br />

onsite until the AMH physical. WCH will provide additional information regarding this.<br />

EQUIPMENT<br />

*The John Deere 220 excavator is planned to be leaving the site; the 330 excavator will be<br />

equipped to utilize the CRATER. The 6th haul truck is on hold for use until final certification<br />

data is provided.