118-K-i Burial Ground Remediatlon Project<br />

Daily Report<br />

Date: Wednesday,July 08, 2009<br />

Prepared By: Ron Belden Start Time: 6:00 AM<br />

Finish Time: 4:30 PM<br />

Weather: Partly cloudy, winds 15-25 in the afternoon, high: 880 F, low: 520 F.<br />

Production Summary<br />

Manpower Summary<br />

Straight<br />

Estimated BCMV Sorted: BCM Time Overtime<br />

Estimated Tons Loaded: Tons Classification Hrs Hirs<br />

No. of Containers Loaded: Cans Operators<br />

No. of Containers Shipped: Cans Laborers<br />

No. of Anomalies Handled: 0 Each Teamsters<br />

Anomaly Characterization: 0 Crew Hrs. Mechanic<br />

Total 0.00 0.00<br />

Equipment Summary<br />

Hitachi 450 #1 hrs. Rock Truck hrs.<br />

Hitachi 450 #2 h rs. Water Truck #1 h rs.<br />

Hitachi 330 #1 h rs. Water Truck #2 h rs.<br />

Hitachi 330 #2 hrs. Road Grader h rs.<br />

Hitachi 225 #1 h rs. Front End Loader hrs.<br />

Hitachi 225 #2 hrs. Fork Lift h rs.<br />

Shuttle Truck #1 h rs. Shear h rs.<br />

Shuttle Truck #2 h rs. hrs.<br />

Shuffle Truck #3 hrs. hrs.<br />

Shuttle Truck #4 h rs. h rs.<br />

POD Summary<br />

Meeting @ 0600 hrs. Safety topic discussed heat stress and how to prevent it. Work scope was discussed. Some concern<br />

expressed over congestion and personnel working in close proximity to equipment. Excavator operators were reminded that they<br />

control their work area and will make sure everyone is following their direction when in that area.<br />

Work Activity Summary<br />

Gross and secondary sorting in Trenches J, L, C and K. Loading EROF containers from Trenches C, J and D. 15 Boxes of liners<br />

were delivered @ 1415 hrs. Handled 5 anomalies, Characterized 4 anomalies in the morning (3.5 crew hours.)<br />

All soils disturbed today were treated with a soil fixative at the end of the shift.<br />

SafetyfrraininaJAccident/lncident Activities<br />

Monthly GFCI Inspections performed. All were functioning properly.<br />

Excavation Inspections<br />

Performed by Ron Belden @ 0645 hrs immediately after the POD. All excavations were approved for personnel entry. This was<br />

communicated to the workforce via radio.<br />

Air Monitor Inspections<br />

Performed by Ron Belden (0 0545 hrs prior to the POD. All monitors were running.<br />

Delays (Concurrence y WCH:<br />

Rad~on Equip: No. 2 sorting crew down for 2.5 hours (0845-1115 hrs) while the CRATER system was not functioning.<br />

Wind: Shutdown at 1500 hrs due to excessive winds (1 hour).<br />

Other<br />

NorthPoint Electrical was onsite to troubleshoot the Frisking Tent lighting.