Progress Review Meeting<br />

Page 6<br />

activities. WCH commits to providing a response to DDI by 7/19. (7/14) This will be issued by<br />

WCH will have response to DDI by 7/22. (7/20) WCH sent a letter in response - these costs are<br />

included in Exhibit "D" of the contract. DDI will be submitting a more detailed REA in response<br />

to this letter. (7/27) DDI is reviewing letter with legal counsel. Will follow up to WCH with a<br />

revised request. (8/3) No change. (8/17)<br />

XII.<br />

TECHNICAL DATA SUBMITTALS/STATUS<br />

* See attached.<br />

* WCH requests as-built drawings of the energized water system. No update (5/4). No update.<br />

(5/11) SDR provided, no update. (5/18) No update. (5/25) No update. (6/8) Water line as-builts<br />

are being marked up for WCH review prior to being submitted. WCH stressed that the as-builts<br />

need to indicate the location of the water lines from hook up at the fence to the high tower. (6/8)<br />

No change. (6/15) No change. (6/22) WCH to provide new drawing number for the as-built<br />

drawing. (6/29) WCH will also provide a CADD base file to DDI for this drawing. (7/6) DDI<br />

has received base CADD file and is in process of updating drawing. They commit to<br />

resubmitting drawing by 7/21. (7/14) DDI is working with their design group to get the drawings<br />

updated, but DDI has had issues with the CADD file, submission bumped to 7/26. (7/20) DDI is<br />

reviewing the cost of drawing; anticipate submittal of drawing by 8/3. (7/27) Submittal delivery<br />

has been pushed to 8/12. (8/3) Drawing should be available for DDI review from their sub-tier by<br />

8/18, they will submit to WCH for review no later than 8/23. (8/10)<br />

* WCH return traffic control drawings to DDI, status 2. DDI will be resubmitting soon<br />

incorporating the WCH comments. DDI to submit this week. Drawings are with North Point for<br />

revision and will be resubmitted upon their return. DDIis well beyond the 30-day resubmission<br />

for updated drawings. WCH will be issuing an SDR regarding this issue. DDI has indicated they<br />

are working on a deficiency letter which will be submitted to Watts for this and several other<br />

deficiencies. (5/11) No update. (5/18) No update. (5/25) WCH received traffic control submittal<br />

6/3 and is in review of same. (6/8) WCH has returned to DDI status 2. (6/22) No change. (6/29)<br />

They commit to resubmitting drawing by 7/21 (7/14). DDI will install signs to match the traffic<br />

control drawing then resubmit. (7/20) Drawing should be available for DDI review from their<br />

sub-tier by 8/18, they will submit to WCH for review no later than 8/23. (8/10)<br />

XIII. CHANGE NOTICES/STATUS/CHANGE ORDERS<br />

* See attached.<br />

XIV.<br />

XV.<br />

CORRESPONDENCE (since last meeting)<br />

*Weekly Progress Review Meeting Minutes of 8/17/2010<br />

IN VOICE AND PAYMENT STATUS<br />

* DDI requests a copy of Contract Modifications for completed change notices. (8/10) No update.<br />

(8/17)<br />

" DDI inquired about a partial release of retainage from the mobilization pay item. WCH will<br />

evaluate. (8/10) No update. (8/17)