Sludge Treatment Project Engineered Container Retrieval and Transfer System December 2011<br />

PART 3 - EXECUTION<br />

3.1 APPROVAL<br />

A. Work shall not start until system design has been approved by the Hanford Fire Marshal’s<br />

Office.<br />

B. Work shall be conducted under a permit issued by the Hanford Fire Marshal’s Office.<br />

C. Systems shall not be connected to the 100K Area water system until approved by the Hanford<br />

Fire Marshal’s Office.<br />

3.2 EXAM<strong>IN</strong>ATION<br />

A. Prior to installation carefully inspect installed Work of other trades, whether pre-existing or part<br />

of this Project, and verify that such work is complete to the point where installation of<br />

sprinkler system may start.<br />

B. Notify the Subcontract Technical Representative (STR) should conditions exist, not resulting<br />

from Work of this Project, that prohibits the installation from conforming to referenced<br />

codes, regulations, standards and approved design.<br />

C. Install materials and equipment that are free of moisture, scale, corrosion, dirt and other foreign<br />

materials.<br />

3.3 EARTHWORK<br />

Earthwork shall be performed in accordance with applicable provisions of Section 31 2000 EARTH<br />

MOV<strong>IN</strong>G.<br />

3.4 <strong>IN</strong>STALLATION REQUIREMENTS<br />

The installation shall be in accordance with the applicable provisions of NFPA 13, NFPA 24 and publications<br />

referenced therein.<br />

3.5 <strong>IN</strong>SPECTION BY FIRE PROTECTION SPECIALIST<br />

The Fire Protection Specialist shall inspect the sprinkler system twice during the installation to assure<br />

that the sprinkler system is installed in accordance with the contract requirements. The Fire Protection<br />

Specialist shall witness the preliminary and final tests, and shall sign the test results. The Fire Protection<br />

Specialist, after completion of the system inspections and a successful final test, shall certify in<br />

writing that the system has been installed in accordance with the contract requirements. Any discrepancy<br />

shall be brought to the attention of the STR in writing, no later than three working days after the<br />

discrepancy is discovered.<br />

3.6 ABOVEGROUND PIP<strong>IN</strong>G <strong>IN</strong>STALLATION<br />

A. General:<br />

1. Install system in accordance with<br />

Contract 44577 KW Annex - Rev. D 44577-CSI-SPEC-001 211313 - 11