Sludge Treatment Project Engineered Container Retrieval and Transfer System January 2012<br />

2. Comply with ASME B31.3, Normal Service Category, as applicable, for materials, products,<br />

and installation.<br />

3. Safety Valves: ASME Boiler and Pressure Vessel Code: Section VIII, Division 1. Safety<br />

valves shall bear the appropriate ASME label.<br />

4. Pressure Vessels: ASME Boiler and Pressure Vessel Code: Section VIII, Division 1.<br />

Pressure vessels shall bear the appropriate ASME label.<br />

5. Flange set-up, alignment, bolt/stud installation and material requirements: comply with<br />

ASME PCC-1-2010.<br />

J. Steel Support Welding: Qualify processes and operators according to AWS D1.1/D1.1M,<br />

"Structural Welding Code – Steel," and Section 055000, Metal Fabrications. Perform 100%<br />

visual examination of final weld joints for piping supports, anchors, and all other structural<br />

welds shall be in accordance with AWS D1.1 and D1.6 as applicable for statically loaded<br />

structures.<br />

K. Testing Agency Qualifications: An independent testing agency, with the experience and<br />

capability to conduct the piping testing indicated, that is an NRTL as defined by OSHA in<br />

29 CFR 1910.7, and that is acceptable to the Buyer.<br />

L. Electrical Components, Devices, and Accessories: Listed and labeled as defined in NFPA 70,<br />

Article 100, by a testing agency acceptable to the Buyer, and marked for intended use.<br />

M. All items and processes are subject to review, inspection, or surveillance by the Buyer's Quality<br />

Assurance or Engineering Representatives at the Vendor's facility or the Vendor's subcontractor<br />

facility.<br />

N. Hold, Witness, and Verification points shall be identified in the Fabrication, Inspection and Test<br />

Plan. Prerequisites to verification points: Ensure that personnel have completed inspections and<br />

approved portions of work in accordance with specification requirements before notifying<br />

Buyer.<br />

O. Seller shall control fabrication, assembly, inspection, testing, and related activities, performed in<br />

shops and at worksite, in accordance with Fabrication, Inspecting and Test Plan.<br />

1.5 DEF<strong>IN</strong>ITIONS<br />

A. Refer to Section 011100, Summary of Work, for definition of general requirements that apply to<br />

all specification sections prepared for this Project.<br />

B. Specific definition applicable to this section include:<br />

1. Buyer: the contractor responsible for managing the design, procurement, and construction<br />

of the K-West Basin Modification Annex Project.<br />

Contract 44577 KW Annex – Rev E. 44577-CSI-SPEC-001 402319-6