Sludge Treatment Project Engineered Container Retrieval and Transfer System December 2011<br />

3.7 UNDERGROUND PIP<strong>IN</strong>G <strong>IN</strong>STALLATION<br />

The fire protection water main shall be laid, and joints anchored, in accordance with NFPA 24. Minimum<br />

depth of cover shall be 42 inches, in accordance with the DOE Fire Protection Handbook, Hanford<br />

Chapter. The supply line shall terminate inside the building with a flanged piece, the bottom of<br />

which shall be set not less than 6 inches above the finished floor. A blind flange shall be installed<br />

temporarily on top of the flanged piece to prevent the entrance of foreign matter into the supply line.<br />

A concrete thrust block shall be provided at the elbow where the pipe turns up toward the floor. In addition,<br />

joints shall be anchored in accordance with NFPA 24 using pipe clamps and steel rods from the<br />

elbow to the flange above the floor and from the elbow to a pipe clamp in the horizontal run of pipe.<br />

Buried steel components shall be provided with a corrosion protective coating in accordance with<br />

AWWA C203. Pipe within 5 ft of the foundations shall be of ductile iron. Piping more than 5 feet<br />

outside the building walls shall meet the requirements of Section 331116 FACILITY WATER<br />

DISTRIBUTION PIP<strong>IN</strong>G.<br />

3.8 EARTHWORK<br />

Earthwork shall be performed in accordance with applicable provisions of Section 31 2000 EARTH<br />

MOV<strong>IN</strong>G.<br />

3.9 ELECTRICAL WORK<br />

Alarm signal wiring connected to the building fire alarm control system shall be in accordance with<br />

Section 28 3100 FIRE DETECTION AND ALARM. Wiring color code shall remain uniform<br />

throughout the system and shall meet the requirements of the DOE Fire Protection Handbook, Hanford<br />

Chapter.<br />

3.10 PIPE COLOR CODE MARK<strong>IN</strong>G<br />

Color code marking of piping shall be as specified in Section 099600 SPECIAL COAT<strong>IN</strong>GS.<br />

3.11 EQUIPMENT <strong>IN</strong>STALLATION<br />

Install devices or equipment not specifically covered by these Specifications in accordance with manufacturer's<br />

instructions.<br />

3.12 CONNECTIONS TO EXIST<strong>IN</strong>G SYSTEMS<br />

A. Final connection of new systems to existing underground piping systems will be made by with<br />

materials furnished by the Subcontractor.<br />

B. Final connection of new systems to other existing systems above grade shall be done by the<br />

Subcontractor after contacting the STR who will implement the Site Fire Protection<br />

Impairment Procedure. Do all final connections of this type with only one outage per<br />

existing system.<br />

3.13 PRELIM<strong>IN</strong>ARY TESTS<br />

The system, including the underground water mains and the aboveground piping and system components,<br />

shall be tested to assure that equipment and components function as intended. The underground<br />

and aboveground interior piping systems and attached appurtenances subjected to system working<br />

Contract 44577 KW Annex - Rev. D 44577-CSI-SPEC-001 211313 - 14