3rd International Scientific and Professional Conference<br />

CORRIDOR <strong>10</strong> - a sustainable way of integrations<br />

the train that starts before the calculation period begins, but then proceeds to pass part or all<br />

of the calculation step in the calculation period (2.c.) (only in ÖBBmethod, in DB-method this<br />

train is discarded).<br />

Figure 5: Path compression [8]<br />

In cases 2.a. and 2.b., the start of the block section occupation in the first block section of the<br />

calculation step is moved to the start of the calculation period. In example 2.c., the train path remains<br />

in the same position. When condensing the timetable the following train is pushed to the block section<br />

occupation of train ahead, but the starting time of this train inside of the calculation step is maximum<br />

adjusted up to the start of the calculation period, so that gaps between the block section occupations<br />

may occur. Compression always begins at the start of the calculation period. Timetable compression<br />

stops upon reaching the train whose first occupation is fully within the calculation period and is<br />

performed until its final occupation inside of the calculation step.<br />

5.4 The resulting infrastructure occupation (line Pragersko-Ormož)<br />

The resulting infrastructure occupation time is measured at the beginning of the calculation step. The<br />

infrastructure occupation time is defined as the time from the start of the calculation period to:<br />

the end of the first occupation of the final train in the ÖBB-method,<br />

the beginning of first block section occupation of the "Dummy-train" in the DBmethod<br />

The results of the compressed paths for line Pragersko-Ormož are displayed in the figure below.<br />

Figure 6: Calculating the infrastructure occupation<br />

Belgrade, 2012 206