3rd International Scientific and Professional Conference<br />

CORRIDOR <strong>10</strong> - a sustainable way of integrations<br />

The works are divided into 2 stages. The first stage is formed by the section Nové Mesto nad Váhom -<br />

Trenčianske Bohuslavice, that consists of the modernisation of the RS Trenčianske Bohuslavice,<br />

where on the turnout layout of Žilina direction the first crossover from turnouts of 1:26,5-2500 on ŽSR<br />

lines is fitted, and there is also a dual rail tunnel under Turecký vrch mountain and the construction of<br />

first ever section with the solid track on ŽSR lines- in the tunnel and on its glacis. Within the<br />

modernisation, 1 new railway bridge, 1 new road bridge, and 1 281m of noise walls will be built.<br />

4 existing railway bridge objects will be reconstructed.<br />

The plans for construction of the tunnel Turecký vrch, which overall length in the axis is 1775 m,<br />

started 45 years ago. The excavated part of the tunnel is 1 740 m long, the remaining 35 m (25 m on<br />

the southern and <strong>10</strong> m on the northern pillar) are realized in the open building pit and later on<br />

imbanked in a way that the terrain over the tunnel would return to its original level as much<br />

as possible. The direction ratios of the track in the tunnel are designed for the speed 200 km.h -1 and<br />

are formed by 2 opposing arches of the radius 2 000 m with a straight interline that is 573 m long.<br />

The designed track gradient in the tunnel is roof-shaped with the gradients +4.887 ‰ and -3.500 ‰,<br />

with regard to the tunnel drainage. In all the length (including the portal sections) there is a uniform<br />

cross-section of the dual rail tunnel with the light radius of the tunnel tube 6.<strong>10</strong> and with the axial<br />

distance of the rails 4.20 m. In the overall tunnel length on both sides the rescue niches are located in<br />

the mutual distances of 20 m. Due to the decrease of the mining works area and also due to durability<br />

and fixed position of the rail or its minimal maintenance in operation, the solid track of type RHEDA<br />

2000 was chosen as a railway superstructure. It is also placed in the parts of the track in front of the<br />

both portals (Fig 7). Out of the overall length 2 280.145 m, besides the tunnel (1 775 m), 34.770 m of<br />

the solid track on is placed on bridges, 425.000 m on earthwork and 45.175 m is formed by the<br />

transition area. The indisputable advantage of this structure is the permanent geometric rail position<br />

and the durability, that is stated by the producers as minimally 60 years. Especially in the tunnels,<br />

where every track closure activity is rather problematic, these properties are invaluable.<br />

Fig. 7 The tunnel Turecký vrch (the northern porta)l under construction with the view<br />

of the solid railroad RHEDA 2000 being built<br />

The second stage consists of the modernisation of the railway stations Trenčianske Bohuslavice and<br />

Melčice, of 2 interstational sections Trenčianske Bohuslavice – Melčice and Melčice – Zlatovce and<br />

railway stop Kostolná-Záriečie (Fig. 8). Within the modernisation 1 new railway bridge, 5 new road<br />

bridges, 3 underpasses in the railway stations for the passengers and 3 underpasses for public as well<br />

as 1 281 m of noise walls will be built. 6 existing railway bridge objects will be reconstructed.<br />

.<br />

Fig. 8 Railway stop Kostolná-Záriečie<br />

The section Zlatovce – Trenčianska Teplá (3. stage) involves modernisation of 11.952 km of railway<br />

track. In the respective section 2 railway stations are located, namely Zlatovce and Trenčín. After<br />

modernisation they will merge into RS Trenčín with the districts Trenčín and Zlatovce. The<br />

interstational section between Zlatovce and Trenčin is formed by the new ferroconcrete railway bridge<br />

over the river Váh, 360 m long, that was designed to reach the required speed 140 km.h -1 . Within this<br />

Belgrade, 2012 86