3rd International Scientific and Professional Conference<br />

CORRIDOR <strong>10</strong> - a sustainable way of integrations<br />

modernisation of railway stop Opatová nad Váhom, 9 new underpasses for passengers, 1 new<br />

luggage tunnel, 4 new road bridges, 8 new railway bridges and 7 452 m of noise walls will be built.<br />

2 railway bridges will be reconstructed. The representation of the track routing in the vicinity of RS<br />

Trenčín and the visualization of the most important structures realized in this track section, are<br />

demonstrated by Fig. 9.<br />

Fig. 9 Roting of the modernised section in the vicinity of the future railway station Trenčín,<br />

visualisation of the bridge object over the river Váh and the future railway station Trenčín<br />

The section Trenčianska Teplá – Beluša (4. and 5. stage) involves the modernisation of 20.409 km of<br />

railway line, including the railway stations Trenčianska Teplá, Dubnica, Ilava and Ladce. Within the<br />

modernisation 6 new road bridges will be built and the same number of them will be reconstructed.<br />

4 new railway bridges will be built as well as 7 underpasses in the railway stations for the passengers<br />

and public and there are designed 6 349 m of noise walls. <strong>10</strong> existing railway bridge objects will be<br />

reconstructed.<br />

The section Beluša – Púchov (6. stage) involves the modernisation of 7.000 km of railway line,<br />

including RS Beluša, RS Púchov and the railway stop Dolné Kočkovce. Within the modernisation<br />

4 new railway bridges, 6 new road bridges, 4 underpasses in the railway stations for the passengers<br />

and public will be built and 7 existing railway bridge objects reconstructed. There are also proposed<br />

3 857 m of noise walls along the modernised track.<br />

The modernisation of the railway line in the section Púchov – Žilina is divided into 2 stages. The<br />

section Púchov – Považská Teplá (1. stage) involves the modernisation of 15.800 km of railway line,<br />

including RS Považská Bystrica, reconstruction of the railway stop Nosice and the conversion of RS<br />

Považská Teplá to the railway stop. The section Považská Teplá – Žilina (2. stage) involves the<br />

modernisation of 22.700 km of railway line, including RS Bytča and RS Dolný Hričov and the railway<br />

stops Plevník-Drieňové, Predmier and Horný Hričov. With regard to rather demanding direction ratios<br />

in the stretch Púchov – Považská Bystrica, the change of track routing is necessary – Fig. <strong>10</strong>. In this<br />

track section it will be necessary to span the Nosice canal and the bed of river Váh, to construct a<br />

traverse behind spa Nimnica through the tunnel as well as a subsequent overpass of the rail track<br />

over Nosice dam to the original route. In this section the construction of two tunnels of the overall<br />

length 2,360 km is supposed. The completion of construction works is assumed for 06.2015.<br />

Belgrade, 2012 87