Header Information<br />

Project Name: Substation 56<br />

Name in 7212 : Relocation of Substation 56<br />

Schedule<br />

Project Overview, Objectives and Status<br />

Overview:<br />

Description: Provision of replacement Sub-Station 56 from T1 pier 3.<br />

Ref. Drawings / Images: Location and overview plan<br />

(Refer to Appendix A)<br />

Objectives:<br />

BAA: • Deliver T2B to enable improved passenger and airline<br />

experience.<br />

Airline:<br />

As BAA’s<br />

Status:<br />

BAA Lead Team: Airline Engagement: Strategic Solution or DGS/IGS Stage<br />

<strong>Capital</strong> & Solutions Green Construction<br />

Project Delivery<br />

Current Control Budget:<br />

Total <strong>Capital</strong> Budget (Constant Prices): £3,400,000<br />

Prior to CCRS transfers - Refer to appendix B for cost information detail.<br />

Time:<br />

Brief<br />

Decision:<br />

Start on<br />

Site:<br />

Completion on Site: Operational Use<br />

Commences:<br />

10 / 2007 04 / 2008 06 / <strong>2009</strong> 06/ <strong>2009</strong><br />

Refer to appendix C for programme information detail.<br />

Assumptions:<br />

The following points cover the significant delivery assumptions related to this project;<br />

• With the construction of the T2B and adjacent stands, a requirement exists that part<br />

of Pier 3 be demolished starting October <strong>2009</strong>.<br />

• This project therefore focuses on relocation of Substation 56, and the incorporation<br />

into one facility of both 56 and 87, which will need to be relocated to make way for<br />

the future T2C.<br />

This project forms an integral part of the Toast-rack layout for the Eastern Apron.<br />

• Decommissioning Sub 56 is not part of this project and will be dealt with under the<br />

demolition of Pier 3<br />

• Decommissioning Sub 87 is not part of this project and will be dealt with under the<br />

Outer Pier and Taxiways project<br />

Key Milestones<br />

• Option Decision: 18th October 2007<br />

• Construction Decision: 20 th February 2008<br />

• Target Confirmation: 13 th May 2008<br />

• Completion Confirmation 30th June <strong>2009</strong><br />

Other Key Dates<br />

• <strong>Plan</strong>ned Start on Site: 28th April 2008<br />

• Buildings Weather tight: 5 TH September 2008<br />

• <strong>Plan</strong>ned finish on site: 30th th June <strong>2009</strong><br />

Note: Assumptions stated here are to aid understanding and are not necessarily exhaustive.<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 62