Areas of Disagreement<br />

The following points cover any significant areas of disagreement between BAA and the<br />

Airline Community regarding this project.<br />

• The pier will commence operations in a closed gateroom format. It is the intention<br />

to convert to an open gate lounge format upon T2B Phase 2 opening in 2013<br />

subject to suitable process and technological solutions being agreed between STAR<br />

and BAA to enable STAR to operate from open gaterooms<br />

• Baggage system – the size of the baggage basement required for safeguarding is<br />

dependant upon the type of system to be installed. The current scheme has been<br />

designed upon a tote/dcv system. Star have indicated that they may<br />

want the PTS system being installed in T2A to be extended out to T2B.<br />

Note: Any disagreement noted must be read in the context of the airline engagement status shown above.<br />