Appendix B: Project Delivery: Cost Information<br />

Project Information<br />

Project Name:<br />

Pier 3 Demolition<br />

BCT No.: 6716 OP No.: 22534<br />

AFC Cost Information:<br />

All information extracted from February <strong>2009</strong> month end process<br />

Base Costs: £1,919,112 55 %<br />

On-Cost: £1,276,222 37 %<br />

Risk (R1 Allowance only) £285,712 8 %<br />

Total (As entered into Artemis for Feb 09 Month End) £3,481,046<br />

Commentary:<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 36