The project scope is inclusive of the provision of temp relocations, the refurbishment of<br />

existing areas for relocated facilities and or the re-provision of relocated facilities,<br />

inclusive of VAA Crew facilities, AOSU and SIS into the new pier 7 facility.<br />

Project scope to be inclusive of (expedite and transfer break baggage link) baggage<br />

connectivity T3 to pier 7.<br />

Project scope to exclude any cost for alteration to T3 integrated baggage works.<br />

The project needs to safeguard for inbound DCV from T5D.<br />

The project shall provide a segregated tunnel walkway<br />

between the new pier and Terminal 3.<br />

The vertical circulation that is required by this project will be located within the “pier 6<br />

triangle”<br />

Project scope to be inclusive of the realignment of the adjacent taxi ways and<br />

equipment areas and any resulting requirement to clear these areas and or associated<br />

and adjacent areas.<br />

Permanent decant solutions shall be provided that fit with the western campus master<br />

plan.<br />

• The project will have to be phased because the operation cannot offer up all of the<br />

pier and stands for construction purposes. An outline phasing strategy has been<br />

drawn up based on no more than 4 stands being taken out of operation at one<br />

point in time<br />

• For part of the construction period, passenger connectivity from T3 to the satellite<br />

will be via a coach operation from T3<br />

• Vacant possession of site required – relocation of VAA crew report, AOSU area,<br />

tenant accommodation, L18 baggage facility, staff access to Control Tower. (All<br />

included in this project scope.)<br />

• Project to construct TTS station box, shell and core standard only. Full fit out to be<br />

delivered by the TTS project.<br />

• JX stands – all MARSed, 3 airbridges per stand, 2 PCA units per stand.<br />

• Project enables Pier 6 Phase 2 stands delivery – economies may be achieved by<br />

delivering both projects simultaneously.<br />

Note: Assumptions stated here are to aid understanding and are not necessarily exhaustive.<br />

Operational Issues<br />

Financial Revenue and Operational Cost (Opex) Impact:<br />

Revenue / Opex<br />

Cost Area:<br />

Revenue (+) /<br />

Cost (-) Impact<br />

per Annum:<br />

Commentary:<br />

To be developed<br />

Impact on User Charges: Not included in CIP <strong>2009</strong> Publication<br />

Estimated Per Passenger Cost Impact:<br />

Commentary:<br />

None<br />

Note: Impact on User Charge is subject to a number of complex variables and regulatory decisions and therefore<br />

information is indicative only.<br />

Assumptions:<br />

The following points cover the significant operational assumptions related to this<br />

project;<br />

• BAA security operational efficiencies will be achieved by removal of horizontal<br />

segregation scheme.<br />

Areas of Disagreement<br />

The following points cover any significant areas of disagreement between BAA and the<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 359