Appendix B: Project Delivery: Cost Information<br />

Project Information<br />

Project Name: Relocation of Substation 56<br />

BCT No.: 7212 OP No.: 22916<br />

AFC Cost Information:<br />

All information extracted from February <strong>2009</strong> month end process<br />

Base Costs: £3,097,230 84 %<br />

On-Cost: £517,468 14 %<br />

Risk (R1 Allowance only) £68,680 2 %<br />

Total (As entered into Artemis for Feb 09 Month End) £3,683,378<br />

Commentary:<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 65