Appendix B: Project Delivery: Cost Information:<br />

Project Information<br />

Project Name:<br />

T4 Victor Pier<br />

BCT No.: 8275 OP No.: 23548<br />

AFC Cost Information:<br />

All information extracted from February <strong>2009</strong> month end process<br />

Base Costs: £2,927,463 88 %<br />

On-Cost: £280,255 8 %<br />

Risk (R1 Allowance only) £120,000 4 %<br />

Total (As entered into Artemis for Feb 09 Month End) £3,327,718<br />

Commentary:<br />

Works to be incorporated into adjacent major T4 projects to maximise efficiencies.<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 142