Appendix B: Project Delivery: Cost Information:<br />

Project Name: Eastern Maintenance Base<br />

BCT No.: 7718 OP No.: 23923<br />

AFC Cost Information:<br />

All information extracted from February <strong>2009</strong> month end process<br />

Base Costs: £20,484,023 73 %<br />

On-Cost: £4,548,250 16 %<br />

Risk (R1 Allowance only) £3,000,000 11 %<br />

Total (As entered into Artemis for Feb 09 Month End) £28,032,273<br />

Commentary:<br />

AFC above consists of a base cost of £8.67M for Phase I and £12,87M for Phase II. The make<br />

up of the total base cost and the split between Phase I & Phase II will change once the Options<br />

Paper is approved at the end of this month.<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 240