Header Information<br />

Project Name:<br />

Name in<br />

Schedule<br />

Eastern Apron Airside Road (EAAR)<br />

4202 : EA A/side Rd & Taxilane U/pass<br />

Project Overview, Objectives and Status<br />

Overview:<br />

Description: Grade separated airside road between T2A, B and C.<br />

Ref. Drawings / Images: Overview plan.<br />

Objectives:<br />

BAA: • provide reliable airside journey times<br />

• minimise the risk of conflict between aircraft and vehicles<br />

• provide a more straightforward east to west airside route<br />

Airline:<br />

As BAA’s<br />

Status:<br />

BAA Lead Team: Airline Engagement: Strategic Solution or DGS/IGS Stage<br />

<strong>Capital</strong> & Solutions Green Scheme Design<br />

Project Delivery<br />

Current Control Budget:<br />

Total <strong>Capital</strong> Budget (Constant Prices): £47,700,000<br />

Refer to appendix B for cost information detail.<br />

Time:<br />

Brief<br />

Start on Completion on Site:<br />

Operational Use<br />

Commences:<br />

Decision:<br />

Site:<br />

04/2007 04/2010 Spring 2012 Spring 2013<br />

Refer to appendix C for programme information detail.<br />

Assumptions:<br />

The following points cover the significant delivery assumptions related to this project;<br />

• This Project sits within the Eastern Campus Portfolio of work<br />

• The Project involves the construction of a grade separated airside road to provide<br />

access to the new T2B Terminal and T2C remote stands, which are being developed<br />

as part of the T2A Project.<br />

• The road starts from the roundabout at the SE corner of T2A, at grade, crosses over<br />

the LUL Piccadilly tunnels, descends under the Kilo Taxiway rising towards grade at<br />

T2B descending under the Lima taxiway and rising to grade at T2C<br />

• The scope of work for the road includes:-<br />

• Secant piled retaining walls<br />

• 2 overbridges Kilo and Lima Taxiways<br />

• A 12 m wide road (2 no 5m wide traffic lanes and 1m wide footways each side)<br />

• 4.5m traffic height plus 0.2m clearance zone<br />

• Drainage sumps and pumping<br />

• Electrical supply, distribution and lighting<br />

• Fire protection, Traffic management and control<br />

• The Kilo and Lima taxilane will be operational by Spring 2013. Prior to these dates<br />

the new grade separated road is anticipated to be complete in order not to conflict<br />

with the other construction work. It is also programmed to be carried out in<br />

conjunction with the redevelopment of the southern taxiway.<br />

• The road has been design to fit within physical and logistical constraints especially<br />

the LUL criteria.<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 13