Appendix B: Project Delivery: Cost Information:<br />

Project Information<br />

Project Name:<br />

Immigration Hall Refit<br />

BCT No.: 8563 OP No.: 23826<br />

AFC Cost Information:<br />

All information extracted from February <strong>2009</strong> month end process<br />

Base Costs: £8,393,138 77 %<br />

On-Cost: £1,519,138 14 %<br />

Risk (R1 Allowance only) £947,724 9 %<br />

Total (As entered into Artemis for Feb 09 Month End) £10,860,000<br />

Commentary:<br />

In Scheme Design Stage and a 1st Tier Supplier has not been engaged. Figures include Phase<br />

1 Early Flooring Works<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 108