Header Information<br />

Project Name:<br />

Name in<br />

Schedule<br />

Pier 5 Refurbishment<br />

5094 : Pier 5 Departures Walkway<br />

Project Overview, Objectives and Status<br />

Overview:<br />

Description:<br />

Ref. Drawings / Images:<br />

(Refer to Appendix A)<br />

Refurbish the Pier 5 Departures level walkway to a design<br />

standard which is comparable with Pier 6 and other such<br />

facilities across <strong>Heathrow</strong>.<br />

None<br />

Objectives:<br />

BAA: Provide a significantly enhanced passenger and user<br />

experience on Pier 5 and improve QSM scores<br />

Airline:<br />

Provide a facility equivalent to other facilities at <strong>Heathrow</strong>.<br />

Mou objectives delivered.<br />

Status:<br />

BAA Lead Team: Airline Engagement: Strategic Solution or DGS/IGS Stage<br />

<strong>Capital</strong> & Solutions Green DGS<br />

Project Delivery<br />

Current Control Budget:<br />

Total <strong>Capital</strong> Budget (Constant Prices): £5,500,000<br />

Refer to appendix B for cost information detail.<br />

Time:<br />

Brief<br />

Start on Completion on Site:<br />

Operational Use<br />

Commences:<br />

Decision:<br />

Site:<br />

MM/ YYYY 09/ 2008 04/<strong>2009</strong> 04/<strong>2009</strong><br />

Refer to appendix C for programme information detail.<br />

Assumptions:<br />

The following points cover the significant delivery assumptions related to this project;<br />

The outline scope includes:-<br />

• New ceiling and lighting<br />

• Micam wall panelling system<br />

• New character timber wall panels at gateroom entrances with integrated LCDs<br />

• Introduction of glazing into gateroom entrance walls where appropriate<br />

• Rationalisation and upgrade of fire doors<br />

• New signage and wayfinding as appropriate<br />

Upgrade of M&E where required.<br />

• This project has been classed as a Trigger project with a completion date of 1 st<br />

August <strong>2009</strong>.<br />

• The agreed delivery programme is based on the formation of temporary gateroom<br />

entrances required to facilitate the installation of the new entrance doors and<br />

frontage. The works will be undertaken concurrently with other projects in Terminal<br />

3 and this will be carefully managed to ensure that in total they do not have an<br />

unacceptable effect on the existing operation.<br />

• The Pier 5 gaterooms, the end of Pier 5 and the Pier 5 elbow are not included in the<br />

scope of this project, they are being dealt with separately.<br />

• The majority of the works will be undertaken during the night in order to maintain<br />

the operational integrity of the pier at all times.<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 84