16.10.2014 Views

Capital Investment Plan 2009 - Heathrow Airport

Capital Investment Plan 2009 - Heathrow Airport

Capital Investment Plan 2009 - Heathrow Airport

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Appendix B: Project Delivery: Cost Information<br />

Project Information<br />

Project Name:<br />

Enter the Artemis Project Name here<br />

BCT No.: 2809 OP No.: 23851<br />

AFC Cost Information:<br />

All information extracted from February <strong>2009</strong> month end process<br />

Base Costs: £7,767,426 77 %<br />

On-Cost: £1,522,271 15 %<br />

Risk (R1 Allowance only) £755,954 8 %<br />

Total (As entered into Artemis for Feb 09 Month End) £10,045,651<br />

Commentary:<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 199

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!