Header Information<br />

Project Name:<br />

T3 Pier 5 Demolition / Toast racked Code F Stands<br />

Name<br />

Schedule:<br />

on<br />

FW31 : T3 Pier 5 Demolition / Toast Racked Code F Stands<br />

Project Overview, Objectives and Status<br />

Overview:<br />

Description: • The demolition of Pier 5 (between stand 329 and the<br />

entrance to the phase two extension).<br />

• Creation of a toast rack stand arrangement between the<br />

new Pier 7 and Terminal 3.<br />

• Creation of 13 extra code F stands (7xPS & 6xR) on the<br />

Western apron<br />

• Creation of a code F taxi way between the new Pier 7 and<br />

Terminal 3.<br />

• Create an arrivals and departures link between the new<br />

Pier 7 and the phase 2 extension of P5 (As per existing<br />

width of the re-used phase 2 link, Arrivals & Departures).<br />

This solution assumes that Pier 7 has only a single level of<br />

ramp accommodation and is constructed with a façade that<br />

supports 4 x code F stands and 1 x code E.<br />

Ref. Drawings / Images:<br />

(Refer to Appendix A)<br />

Overview schematic<br />

Objectives:<br />

BAA: • Optimise the operational efficiency of the western apron<br />

taxi ways<br />

• Provide additional code F capacity on the Western apron<br />

• Optimise apron and taxi way efficiency on the western<br />

apron<br />

• Deliver an affordable solution that builds towards a full<br />

toast rack between the main runways<br />

• Re-use the existing phase 2 link bridge to provide an<br />

element of the new link between phase 2 and a new pier<br />

7<br />

Airline:<br />

TBC<br />

Status:<br />

BAA Lead Team: Airline Engagement: Strategic Solution or DGS/IGS Stage<br />

Strategy Red Pre outline<br />

Project Delivery<br />

Current Control Budget:<br />

Total <strong>Capital</strong> Budget (Constant Prices):<br />

Time:<br />

Brief<br />

Decision:<br />

TBC<br />

Refer to appendix B for cost information detail.<br />

Start on<br />

Site:<br />

Completion on Site:<br />

TBC<br />

Refer to appendix C for programme information detail.<br />

Operational Use<br />

Commences:<br />

Assumptions:<br />

The following points cover the significant delivery assumptions related to this project;<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 349