Header Information<br />

Project Name:<br />

Name on<br />

Schedule:<br />

Cargo Tunnel Renovation<br />

FQ06 : Cargo Tunnel Renovation<br />

Project Overview, Objectives and Status<br />

Overview:<br />

Description:<br />

Ref. Drawings / Images:<br />

(Refer to Appendix A)<br />

Objectives:<br />

BAA:<br />

Comprehensive renovation and relife of the existing CTA to<br />

T4 cargo tunnel<br />

None<br />

To bring an essential asset up to date and to extend operating<br />

life for a further 20 years.<br />

Airline:<br />

Ensure the operationally essential airside link is maintained.<br />

Status:<br />

BAA Lead Team: Airline Engagement: Strategic Solution or DGS/IGS Stage<br />

Strategy Red Pre-Outline<br />

Project Delivery<br />

Current Control Budget:<br />

Total <strong>Capital</strong> Budget (Constant Prices):<br />

Time:<br />

Brief<br />

Decision:<br />

TBC<br />

Refer to appendix B for cost information detail.<br />

Start on<br />

Site:<br />

Completion on Site:<br />

TBC<br />

Refer to appendix C for programme information detail.<br />

Operational Use<br />

Commences:<br />

Assumptions:<br />

The following points cover the significant delivery assumptions related to this project;<br />

Scope to include;<br />

- Survey all civil, M&E and all other engineering systems, and response to findings.<br />

- Installation of current UK and EU best practice fire detection and response<br />

systems.<br />

- Complete replacement of the ventilation system.<br />

- Complete road resurfacing including access ramps.<br />

- Repair of all civil engineering elements.<br />

- Recladding of tunnel lining.<br />

- Replacement of all M&E Systems.<br />

- Implementation of best practice tunnel management process.<br />

Works will need to be done in phases with significant (75%) night work with the tunnel<br />

being operational 05:30 to 22:30 daily.<br />

Note: Assumptions stated here are to aid understanding and are not necessarily exhaustive.<br />

Operational Issues<br />

Financial Revenue and Operational Cost (Opex) Impact:<br />

Revenue / Opex Revenue (+) /<br />

Commentary:<br />

Cost Area: Cost (-) Impact<br />

per Annum:<br />

No revenue increase. Negligible opex impact<br />

Impact on User Charges: Not included in CIP <strong>2009</strong> Publication<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 390