Header Information<br />

Project Name: T2A Programme, Phase 1<br />

Name in Various : T2A Buildings Project<br />

Schedule:<br />

Project Overview, Objectives and Status<br />

Overview:<br />

Description:<br />

Ref. Drawings / Images:<br />

(Refer to Appendix A)<br />

Terminal 2 Concourse A (T2A) Phase 1 (and associated<br />

projects)<br />

Artists impression of landside area<br />

Objectives:<br />

BAA: • Improve Passenger experience<br />

• Reduce airline and HAL opex<br />

• Improve operational efficiency<br />

• Co-location airline alliances<br />

Airline:<br />

As BAA’s<br />

Status:<br />

BAA Lead Team: Airline Engagement: Strategic Solution or DGS/IGS Stage<br />

<strong>Capital</strong> & Solutions Green Various<br />

Project Delivery<br />

Current Control Budget:<br />

Total <strong>Capital</strong> budget (Constant Prices): £ 1,142,080,000<br />

Refer to appendix B for cost information detail.<br />

Time:<br />

Brief<br />

Decision:<br />

Start on<br />

Site:<br />

Completion on Site: Operational Use<br />

Commences:<br />

06/<strong>2009</strong> 07/<strong>2009</strong> 08/2013 12/2013<br />

Refer to appendix C for programme information detail.<br />

Assumptions:<br />

The following points cover the significant delivery assumptions related to this project;<br />

T2A replaces outdated facilities in existing Terminal 2 and the forecourt with facilities<br />

primarily for the Star Alliance airlines to enable the consolidation of their operation into<br />

one building at <strong>Heathrow</strong> providing competitive equivalence and to meet the future<br />

needs of Star Alliance passengers and BAA’s requirements for a flexible future proof<br />

capacity.<br />

• The BCT projects captured within this PDS are as follows (Q5/Q6):<br />

• 7767 – T2A Scheme Design Stage £28m<br />

• 8802 – T2A Building £581m<br />

• 8804 – T2A ICS £107m<br />

• 8805 – T2A Baggage £105m<br />

• 7769 – T2A L/S Early Services Relocation £16m<br />

• 7779 – T2A A/S Early Services Relocation £3m<br />

• 8799 – QB Demolition £6m<br />

• 8800 – T2 Demolition £17m<br />

• 8803 – Other CTA Enabling Works £2m<br />

• 8794 – Eastern Campus Leadership Team £58m<br />

Other assumptions:<br />

• Q5 Budget taken from November 08 Artemis Month End Figures<br />

• Future Quinquennia figure covers Q6 Phase 1 programme only<br />

• The vacant possession of T2 and Queens Building, step 6, is achieved on time to<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 72