Appendix B: Project Delivery: Cost Information:<br />

Project Information<br />

Project Name:<br />

CP5<br />

BCT No.: 8801 OP No.: 23996<br />

AFC Cost Information:<br />

All information extracted from February <strong>2009</strong> month end process<br />

Base Costs: £3,761,428 76 %<br />

On-Cost: £801,209 16 %<br />

Risk (R1 Allowance only) £415,608 8 %<br />

Total (As entered into Artemis for Feb 09 Month End) £4,978,245<br />

Commentary:<br />

Base Costs CBI Prelims £721k Fee £148k<br />

Substructures £211k, Frame £251k, Roofing £158k, External Walling £114k, Fit-out £236k,<br />

Primary & Secondary services £415k, External Works £570k,IT/Networks £81K, Specialist<br />

Systems £461k<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 259