Appendix B: Project Delivery: Cost Information:<br />

Project Information<br />

Project Name:<br />

T4 Airline Relocation<br />

BCT No.: 6604 OP No.: 22653<br />

AFC Cost Information:<br />

All information extracted from February <strong>2009</strong> month end process<br />

Base Costs: £22,200,349 73 %<br />

On-Cost: £6,152,185 20 %<br />

Risk (R1 Allowance only) £1,951,361 6 %<br />

Total (As entered into Artemis for Feb 09 Month End) £30,303,895<br />

Commentary:<br />

Significantly extended programme (originally late <strong>2009</strong>, now mid/late 2011) is reflected in<br />

increased oncost provision.<br />

Project Team attempting to significantly reduce both programme and associated oncost:<br />

Opportunity up to £800k.<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 129