enable a start on site 27 October <strong>2009</strong>.<br />

• The baggage solution must be agreed with the Star Airlines and wider airline<br />

community.<br />

• The AFC for the project will meet the target budget for the programme<br />

• Pier service levels of 95% will be achieved within the <strong>Heathrow</strong> East Campus<br />

• HETco and Siemens establish an effective working relationship<br />

• All reserved matters are discharged by July <strong>2009</strong> including LUL approval<br />

• Site lines from the Control Tower are acceptable to NATS<br />

• There is no undue effect on the operational running of the airport during<br />

consultation<br />

Note: Assumptions stated here are to aid understanding and are not necessarily exhaustive.<br />

Operational Issues<br />

Financial Revenue and Operational Cost (Opex) Impact:<br />

Revenue / Opex<br />

Cost Area:<br />

Revenue (+) / Cost<br />

(-) Impact per<br />

Commentary:<br />

Terminal<br />

Building<br />

Annum:<br />

£395m The revenue figure represents the EBITDA<br />

(Revenue less Cost before interest, tax,<br />

depreciation and amortisation costs) for the<br />

first full financial year of operation (2014/15) for<br />

the T2A Terminal building<br />

Impact on User Charges: Not included in CIP <strong>2009</strong> Publication<br />

Estimated Per Passenger Cost Impact:<br />

Commentary:<br />

None<br />

Note: Impact on User Charge is subject to a number of complex variables and regulatory decisions and therefore<br />

information is indicative only.<br />

Assumptions:<br />

The following points cover the significant operational assumptions related to this<br />

project;<br />

• Above is based on estimated operational expenditure (business rates,<br />

maintenance costs etc) that may require further definition in due course.<br />

• The Revenue/Cost data does not include the other part of the Eastern Campus<br />

programme<br />

Areas of Disagreement<br />

The following points cover any significant areas of disagreement between BAA and the<br />

Airline Community regarding this project.<br />

• There is substantial concern from the airlines community in relation to the<br />

baggage solution for T2A and T2B.<br />

• The forecourt for the new T2A is yet to be successfully integrated into the new<br />

MSCP.<br />

Note: Any disagreement noted must be read in the context of the airline engagement status shown above.<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 73