Decision: Site: Commences:<br />

10 / 2007 01 / 2010 07 / 2010 Continuous<br />

Refer to appendix C for programme information detail.<br />

Assumptions:<br />

The following points cover the significant delivery assumptions related to this project;<br />

• A refurbishment programme only with no change to shell and core<br />

• Finishes constrained to the HAL design palette and the standard desk product<br />

established in Terminal 5 to be utilised<br />

• Only passenger facing areas are to be refurbished<br />

• The facility must remain operational throughout construction<br />

• There can be no reduction in the number of functional immigration desks<br />

throughout construction.<br />

Note: Assumptions stated here are to aid understanding and are not necessarily exhaustive.<br />

Operational Issues<br />

Financial Revenue and Operational Cost (Opex) Impact:<br />

Revenue / Opex Revenue (+) /<br />

Commentary:<br />

Cost Area: Cost (-) Impact<br />

per Annum:<br />

Cleaning £0.005M Uplift for glazed finishes & increased numbers of desks<br />

Impact on User Charges: Not included in CIP <strong>2009</strong> Publication<br />

Estimated Per Passenger Cost Impact:<br />

Commentary:<br />

None.<br />

Note: Impact on User Charge is subject to a number of complex variables and regulatory decisions and therefore information is<br />

indicative only.<br />

Assumptions:<br />

The following points cover the significant operational assumptions related to this project;<br />

• The project is a refurbishment of existing facilities<br />

• BAA will provide a facility within which UKBA can meet their revised and improved Service<br />

Level Agreements however there is no commitment from UKBA to uplift immigration staff<br />

accordingly<br />

Areas of Disagreement<br />

The following points cover any significant areas of disagreement between BAA and the<br />

Airline Community regarding this project.<br />

• UKBA are displeased with the ‘standard’ double/ staggered desk arrangement due<br />

to the associated increase in passenger walk time from the queue to the desk. This<br />

desk arrangement is essential to meet requirements for desk numbers and thus to<br />

meet Service Level Agreements. It is understood by all parties that such an<br />

arrangement must be adopted in order to fit the required desk numbers into a<br />

constrained infrastructure. It should be noted that this issue will decline as the<br />

Automated Clearance System is implemented in the future.<br />

• The UKBA desire for the ‘watch-house’ facility to be refurbished however this space<br />

is out of scope and is not a passenger-facing area.<br />

Note: Any disagreement noted must be read in the context of the airline engagement status shown above.<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 106