Header Information<br />

Project Name:<br />

Name in<br />

Schedule:<br />

T5D and Stands<br />

FQ42 : T5D and Stands<br />

Project Overview, Objectives and Status<br />

Overview:<br />

Description:<br />

Ref. Drawings / Images:<br />

(Refer to Appendix A)<br />

Provision of a T5D Satellite building and reconfiguration to<br />

create 14 pier served stands.<br />

Indicative T5 apron layout image in appendix A<br />

Objectives:<br />

BAA: • Provide increased levels of pier service Improve passenger<br />

experience and ASQ/QSM scores.<br />

• Improved taxiway operation by creating further ‘toast<br />

racked’ apron.<br />

• Additional tenant accommodation and retail<br />

opportunities.<br />

Airline: • Improved service offer<br />

• Increased tenant accommodation<br />

• Opportunity for increased single till income.<br />

Status:<br />

BAA Lead Team: Airline Engagement: Strategic Solution or DGS/IGS Stage<br />

Strategy Red Pre-Outline<br />

Project Delivery<br />

Current Control Budget:<br />

Total <strong>Capital</strong> Budget (Constant Prices):<br />

Time:<br />

Brief<br />

Decision:<br />

TBC<br />

Refer to appendix B for cost information detail.<br />

Start on<br />

Site:<br />

TBC<br />

Completion on Site:<br />

Operational Use<br />

Commences:<br />

Refer to appendix C for programme information detail.<br />

The following points cover the significant delivery assumptions related to this project;<br />

Assumptions:<br />

The fuel farm (on T5d site) needs to be removed by 2018, and will be undertaken by<br />

another project.<br />

The T5d cost sheets do not include the cost of basements, which are within the<br />

<strong>Heathrow</strong> Track Transit System cost plan.<br />

Key features of the Pier will be:<br />

• Similar design and layout to T5B, T5C and T2a satellites<br />

• 14 Pier serviced stands (Code F and Code E)<br />

• Ability to operate either closed or open gaterooms<br />

• Vertical segregation of departures / arrivals<br />

• Passenger connectivity via Track Transit System<br />

• Code F stands – all MARSed, 3 airbridges per stand, 2 PCA units per stand.<br />

The following assumptions have been made:<br />

• Fuel farm is relocated, demolished, redirected etc by another project.<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 378