Capital Investment Plan 2009 - Heathrow Airport

Capital Investment Plan 2009 - Heathrow Airport

Capital Investment Plan 2009 - Heathrow Airport

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Segregated pier completed with open gateroom format<br />

Conversion of T2B Phase 1 (North) from closed gaterooms to open gatelounge<br />

Local flight connections centre<br />

Retail provision of approx 1,275m 2<br />

Total CIP provision of 3,600m 2 in 3 lounges<br />

Approx 4,000m 2 of ramp accommodation<br />

Basement structure for “traditional” transfer baggage facility (connecting tunnels and fit<br />

out by C&B).<br />

Demolition of Europier & Eurolink South<br />

Connectivity and Baggage<br />

Vertical passenger circulation within T2B for underground connectivity<br />

Safeguarding in T2B for future TTS (all fit out by future project) – assumed transfer of<br />

funds from PSDH of £73.6m in Q5 for this element of work<br />

T2A-T2B passenger tunnel with segregated corridors<br />

Interim vertical circulation core outside T2A connecting to passenger tunnel<br />

The baggage basement has been sized to safeguard for the future installation of a<br />

conventional baggage system.<br />

Stands & Taxiways<br />

Provision of 2 No. JX stands and associated taxiway (Q6)<br />

Scope Exclusions<br />

TTS and baggage tunnels beneath Lima and Kilo Taxiways<br />

Safeguarding for Powered Trolley System baggage facility in lieu of traditional<br />

Note: Assumptions stated here are to aid understanding and are not necessarily exhaustive.<br />

Operational Issues<br />

Financial Revenue and Operational Cost (Opex) Impact:<br />

Revenue / Opex Revenue (+) /<br />

Commentary:<br />

Cost Area: Cost (-) Impact<br />

per Annum:<br />

Cleaning £1.0M Stand alone cost, not incremental<br />

Maintenance £1.3M Stand alone cost, not incremental<br />

Staffing £2.8M Stand alone cost, not incremental. Costs mainly<br />

associated with Connections Centre.<br />

Rates £2.1M Stand alone cost, not incremental<br />

Utilities £1.0M Stand alone cost, not incremental<br />

Property<br />

Income<br />

£3.8M Stand alone cost, not incremental. Income from<br />

CIP Lounges and accommodation<br />

Retail Income £1.2M Stand alone, not incremental. Income from retail<br />

units. Media income not included as allowed for<br />

within T2A package.<br />

Impact on User Charges: Not included in CIP <strong>2009</strong> Publication<br />

Estimated Per Passenger Cost Impact:<br />

Commentary:<br />

None.<br />

Note: Impact on User Charge is subject to a number of complex variables and regulatory decisions and therefore<br />

information is indicative only.<br />

Assumptions:<br />

The following points cover the significant operational assumptions related to this<br />

project;<br />

• The pier will operate in an open gatelounge format, subject to suitable process and<br />

technological solutions being agreed between STAR and BAA to enable STAR to<br />

operate from open gaterooms<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 38