Header Information<br />

Project Name:<br />

Name in<br />

Schedule<br />

Terminal 4 Refurbishment (CSA etc)<br />

6693 : Terminal 4 Refurbishment<br />

Project Overview, Objectives and Status<br />

Overview:<br />

Description:<br />

Ref. Drawings / Images:<br />

(Refer to Appendix A)<br />

The T4 Refurbishment project comprises 3 main areas:<br />

• Expansion and refurbishment of the Central Search Area<br />

(CSA).<br />

• Reconfiguration of retail units and general refurbishment<br />

of the International Departures Lounge (IDL).<br />

• Refurbishment of elements within the Arrivals journey.<br />

CSA: Overview plan<br />

IDL: Overview plan<br />

Arrivals: No plan<br />

BAA: • Increase capacity/efficiency of the CSA.<br />

• Maintain retail income by re-accommodating retail<br />

concessionaires affected by the CSA refurbishment.<br />

• Enhance the passenger experience .<br />

Airline: • Reduce processing times for passengers through CSA<br />

• Enhance customer service standards.<br />

Status:<br />

BAA Lead Team: Airline Engagement: Strategic Solution or DGS/IGS Stage<br />

<strong>Capital</strong> Projects Amber CSA/IDL – Construction decision<br />

Arrivals – Brief decision<br />

Project Delivery<br />

Current Control Budget:<br />

Total <strong>Capital</strong> Budget (Constant Prices): £22,100,000<br />

Refer to appendix B for cost information detail.<br />

Time:<br />

Brief<br />

Start on Completion on Site:<br />

Decision:<br />

CSA/IDL: 03/2007<br />

Arrivals : TBC<br />

Site:<br />

01/<strong>2009</strong><br />

06/<strong>2009</strong><br />

10/<strong>2009</strong><br />

06/2010<br />

Refer to appendix C for programme information detail.<br />

Operational Use<br />

Commences:<br />

10/<strong>2009</strong><br />

06/2010<br />

Assumptions:<br />

The following points cover the significant delivery assumptions related to this project;<br />

• Phased closure of a portion of current CSA, whilst refurbishment is carried out.<br />

• Vacation of a large portion of current retail units by concessionaires.<br />

• Vacation of Terminal 4 by British Airways on agreed dates<br />

Note: Assumptions stated here are to aid understanding and are not necessarily exhaustive.<br />

Operational Issues<br />

Financial Revenue and Operational Cost (Opex) Impact:<br />

Revenue / Opex<br />

Cost Area:<br />

Revenue (+) /<br />

Cost (-) Impact<br />

per Annum:<br />

Commentary:<br />