Appendix B: Project Delivery: Cost Information:<br />

Project Information<br />

Project Name:<br />

Next Generation Autotray System<br />

BCT No.: 9105 OP No.: 24230<br />

AFC Cost Information:<br />

All information extracted from February <strong>2009</strong> month end process<br />

Base Costs: £3,737,000 74 %<br />

On-Cost: £909,000 18 %<br />

Risk (R1 Allowance only) £404,000 8 %<br />

Total (As entered into Artemis for Feb 09 Month End) £5,050,000<br />

Commentary:<br />

This project underwent Brief Decision in December 2008, and is currently in the Options<br />

Development stage. The cost planning process has not yet commenced, and as such the<br />

figures above are provisional and are based on a % calculation of the total AFC.<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 263