Header Information<br />

Project Name:<br />

Name in<br />

Schedule<br />

South East Taxiway<br />

3817 : South East Taxiways<br />

Project Overview, Objectives and Status<br />

Overview:<br />

Description:<br />

Upgrade and realignment of taxiways in SE portion of Eastern<br />

Airfield.<br />

Ref. Drawings / Images: Overview plan<br />

Objectives:<br />

BAA: • Enhanced airfield operations especially on 27L holds.<br />

• Improved airline operation.<br />

• Improved passenger experience.<br />

Airline:<br />

As BAA’s<br />

Status:<br />

BAA Lead Team: Airline Engagement: Strategic Solution or DGS/IGS Stage<br />

<strong>Capital</strong> & Solutions Green Manufacture & Assemble<br />

Project Delivery<br />

Current Control Budget:<br />

Total <strong>Capital</strong> Budget (Constant Prices): £60,800,000<br />

Refer to appendix B for cost information detail.<br />

Time:<br />

Brief<br />

Start on Completion on Site:<br />

Operational Use<br />

Commences:<br />

Decision:<br />

Site:<br />

10/2006 01/2008 10/2010 See below<br />

Refer to appendix C for programme information detail.<br />

Assumptions:<br />

The following points cover the significant delivery assumptions related to this project;<br />

• This project forms part of the Eastern Campus programme, providing airfield<br />

infrastructure to support the Eastern Apron Development and full Code F (A380)<br />

operations. It is a key enabler, and on the critical path, for the T2A and T2B<br />

developments; creating the necessary construction space and providing pit and duct<br />

routes for services. The project phasing is aligned with the requirements of these<br />

projects.<br />

• This project creates the required space for the Eastern Apron Development by<br />

realigning the main Alpha and Bravo taxiway system in the South east corner of the<br />

airfield, including: new taxiway construction, reconfigured 27L holds, and provision<br />

of major service ducts for T2A and T2B.<br />

• The business benefit of this project relates to: maximising the developable space on<br />

the airfield, providing re-lifed infrastructure, creating a Code F (A380) compatible<br />

taxiway system, and maintaining sufficient holding capacity for an efficient runway<br />

operation. The reconfigured 27L Hold solution does not compromise potential longterm<br />

future Eastern Apron Developments.<br />

• The phases of this project will be delivered on the following dates:<br />

• Phase 1A: 23 rd January <strong>2009</strong><br />

• Phase 1C: 23 rd January <strong>2009</strong><br />

• Phase 2: 19 th April <strong>2009</strong><br />

• Phase 3A: 16 th June <strong>2009</strong><br />