Header Information<br />

Project Name:<br />

Name in<br />

Schedule<br />

T2B North East Stands & taxilanes<br />

7206 : T2B NE Stands & Taxilanes<br />

Project Overview, Objectives and Status<br />

Overview:<br />

Description:<br />

Ref. Drawings / Images:<br />

Provision of stands and realigned taxiways to the NE of T2B<br />

Overview plan<br />

Objectives<br />

BAA: • Enhance airfield operations especially on 27L.<br />

• Improved airline operations .<br />

• Improved passenger experience.<br />

Airline:<br />

As BAA’s<br />

Status:<br />

BAA Lead Team: Airline Engagement: Strategic Solution or DGS/IGS Stage<br />

<strong>Capital</strong> & Solutions Green Manufacture & Assemble<br />

Project Delivery<br />

Current Control Budget:<br />

Total <strong>Capital</strong> Budget (Constant Prices): £14,200,000<br />

Refer to appendix B for cost information detail.<br />

Time:<br />

Options<br />

Start on Completion on Site:<br />

Operational Use<br />

Commences:<br />

Decision:<br />

Site:<br />

03/2007 04/2008 10/<strong>2009</strong> 06/<strong>2009</strong> onwards<br />

NB: phased.<br />

Refer to appendix C for programme information detail.<br />

Assumptions:<br />

The following points cover the significant delivery assumptions related to this project;<br />

• The T2B NE Stands & Taxilanes project is part of the Eastern Campus Programme.<br />

• The scope of the project is to supply, install, test, commission and handover the<br />

Apron work outlined below:<br />

1. Construction of 3 new permanent stands 249, 248 & 247.<br />

2. Construction of HoS, interstand and Delta crossing roads.<br />

3. Services infrastructure below Apron to meet needs of stands and MF Pier.<br />

4. Tie into existing taxilane to the East.<br />

5. Tie into new MFPN VCC (Node) Buildings including parking areas and<br />

footpaths.<br />

6. Landscaping of grass area to the North.<br />

NB: AFC now includes significant approved scope change in terms of NW enabling<br />

works being undertaken by this project.<br />

• The phases of this project will be delivered on the following dates:<br />

• Stand 249 – 16 June <strong>2009</strong> (as a remote stand)<br />

• Stands 247 & 248 – 10 Aug <strong>2009</strong> (as remotes).<br />

• Overall Project completion – October <strong>2009</strong>.<br />

Note: Assumptions stated here are to aid understanding and are not necessarily exhaustive.<br />

Operational Issues<br />

Internal File Name: 0903XX-CIP <strong>2009</strong> Main Document-V71-IG 206