Foundation Fieldbus 35-9<br />

Field<br />

Instrument<br />

X<br />

Junction box<br />

Typical network diagram<br />

Control room<br />

Segment No.<br />

Marsh Cab. Barrier I/O terminal Module Control logic<br />

N N N 7+ 6+<br />

B<br />

B B 8 T 5<br />

9– 4–<br />

3+<br />

PR # PR #<br />

2–<br />

9121 1<br />

X UCN<br />

X<br />

Modnum<br />

File X<br />

JX<br />

card X<br />

X Slotnum<br />

X<br />

10<br />

–<br />

Power +<br />

supply<br />

X<br />

File<br />

JX<br />

card<br />

X<br />

X<br />

X<br />

X T 4<br />

N<br />

B<br />

1<br />

2<br />

3<br />

T<br />

5<br />

6<br />

7<br />

8<br />

Terminator<br />

FIGURE 35.6<br />

Typical project diagram.<br />

during construction with simple procedures such as insuring that all connections are properly tightened<br />

and checking that wires are properly terminated, without short circuits and so on. However, below are<br />

some recommendations to help you get your system operational faster and start making profits.<br />

1. Electrical commissioning<br />

a. Inspect the FF cable coil, check if the ends are protected against water leaks or rain. Measure<br />

the isolation and confirm if it matches the value of the commissioning report.<br />

b. Before connecting the home run cable to any electronics, confirm isolation and the capacitance<br />

measurements and record the values in the commissioning report.<br />

c. Repeat this procedure for each section of the trunk and for all its spurs and record the readings<br />

in the electrical commissioning report.<br />

2. Electronic commissioning<br />

a. Connect the trunk to the coupler installed in the cabinet of the control system and in<br />

all the field junction boxes. Confirm the continuity of the conductor wires and the cable<br />

shield.<br />

b. Check the power for each input and output of the trunk of the field junction boxes; record the<br />

values in the commissioning report.<br />

c. Connect the instruments to the field junction boxes, taking care to isolate the shield at the<br />

instrument.<br />

d. For each spur, check the power at the field junction box terminals and at the instrument terminals;<br />

record these values in the report.<br />

3. Configuration download<br />

a. Contact the people in charge of the configuration of the control system and ask for the<br />

download of the configuration to all the instruments in the segment.<br />

4. Digital <strong>communication</strong> certification<br />

a. After the download of the configuration to all the instruments of the segment, confirm digital<br />

<strong>communication</strong>s using a fieldbus diagnostic tool. Record results for each segment.<br />

b. Create a digital and paper file of the diagnostic tool reports for each segment and complete the<br />

delivery of the segment certification report to the plant commissioning team.<br />