UWS-13 Sewerage Project at Jalandhar (ACA 2009-10)<br />

416<br />

Outlay– Rs. 1.00 lac<br />

11.6.22 One time ACA of Rs. 25.00 crore approved for Sewerage Project at Jalandhar<br />

had been provided in the Revised Estimate 2009-10. For this purpose, a token provision of<br />

Rs. 1.00 lac was provided in the Annual Plan 2010-<strong>2011</strong>. However in the Revised Estimate<br />

of 2010-11, Rs. 2500.00 lac has been provided as one-time ACA. An outlay of Rs. 1.00 lac<br />

is provided as a token provision for the Annual Plan <strong>2011</strong>-<strong>12</strong>.<br />

.UWS-16 Converting of Ganda Nallah into under ground storm water sewer at<br />

Amritsar<br />

Outlay –Rs. 423 .00 lac<br />

11.6.23 The Ganda Nallah flowing in the Abadi of Medical Enclave, Akash Avenue<br />

upto Bye-pass road may be converted into RCC storm water sewer. The total estimate for<br />

cost of Rs. 1023.00 lac has been prepared and sent to PIDB for its approval. However, the<br />

scheme has been approved by PIDB in its 89 th meeting which was held on 3.8.09 and a first<br />

installment of Rs. 300.00 lac has been released by PIDB. For this purpose, an outlay of Rs.<br />

600.00 lac is provided in the Annual Plan 2010-<strong>2011</strong> against which expenditure of Rs.<br />

175.57 lac has been incurred. An outlay of Rs. 423.00 lac is provided for the Annual Plan<br />

<strong>2011</strong>-<strong>12</strong>.<br />

UWS-17 Cleaning of Budha Nallah and restoration of ecology of Holy Bein<br />

Outlay –Rs. 500.00 lac<br />

11.6.24 Disposal of untreated waste into Budha Nallah, which is passing through the<br />

heart of Ludhiana City, has become a source of nuisance to the localities adjoining it. It is<br />

also causing pollution of under ground water. Absence of Dissolved Oxygen in the Nallah<br />

has affected the aquatic life in it as well as the river Satluj. The state government has<br />

decided to clean the Budha Nallah by providing Sewerage System & Sewage Treatment<br />

Plants (STPs), upgradation of STPs and Main pumping stations of various towns and laying<br />

of sewers in localities adjoining Budha Nallah.<br />

11.6.25 An outlay of Rs. 50.00 crore as one time ACA has been allocated for cleaning<br />

of Budha Nalla and Restoration of Ecology of Holy Bein during 2009-10. In a meeting held<br />

by Chief Secretary, <strong>Punjab</strong> on 27/8/09, it had been decided that Department of Local bodies<br />

would act as A.D for obtaining the proposal from the concerned Departments and their<br />

consolidation for the review of Chief Secretary, <strong>Punjab</strong>. For implementation of this project,