PART 3 - EXECUTION<br />

3.1 CONTRACTOR'S REVIEW<br />

A. Action and Informational Submittals: Review each submittal and check for coordination<br />

with other Work of the Contract and for compliance with the Contract Documents.<br />

Note corrections and field dimensions. Mark with approval stamp before submitting to<br />

Architect.<br />

3.2 ARCHITECT'S ACTION<br />

A. General: Architect will not review submittals that do not bear Contractor's approval<br />

stamp and will return them without action.<br />

B. Architect’s review is for general conformance and compliance with the design concept,<br />

drawings and specifications only. Any action noted does not waive any requirements of<br />

the Contract Documents. Verification of details, and/or dimensions, quantities,<br />

coordination of trades, the maintenance of the highest standards of safety and the<br />

satisfactory performance of the work are the Contractor’s complete and total<br />

responsibility.<br />

C. Action Submittals: Architect will review each submittal, make marks to indicate<br />

corrections or revisions required, and return it. Architect will stamp each submittal with<br />

an action stamp and will mark stamp appropriately to indicate action, as follows:<br />

1. Final Unrestricted Release: Where the submittal is marked “No Exception” the<br />

Work covered by the submittal may proceed provided it complies with the<br />

Contract Documents. Final acceptance will depend on that compliance.<br />

2. Final-but-Restricted Release: Where the submittal is marked “Make Corrections”<br />

the Work covered by the submittal may proceed provided it complies both with<br />

Architect’s notations and corrections on the submittal and the Contract<br />

Documents. Final acceptance will depend on that compliance.<br />

3. Returned for Resubmittal: Where the submittal is marked “Revise and Resubmit,”<br />

do not proceed with the Work covered by the submittal, including purchasing,<br />

fabrication, delivery, or other activity for the product submitted. Revise or<br />

prepare a new submittal per Architect’s notations and corrections. Do not use, or<br />

allow others to use, submittals marked “Revise and Resubmit” at the Project site<br />

or elsewhere where Work is in progress.<br />

D. Informational Submittals: Architect will review each submittal and will not return it, or<br />

will return it if it does not comply with requirements. Architect will forward each<br />

submittal to appropriate party.<br />

E. Incomplete submittals are unacceptable, will be considered nonresponsive, and will be<br />

returned for resubmittal without review.<br />

F. Submittals not required by the Contract Documents may not be reviewed and may be<br />

discarded.<br />

END OF SECTION 01 3300<br />

Project No.: 10145 SUBMITTAL PROCEDURES<br />

550 15th Street Dual Brand Hotel 013300 - 7<br />