3.03 INSTALLATION OF AIR TERMINALS:<br />

A. General: Install air terminals as indicated and in accordance with manufacturer's<br />

installation instructions.<br />

B. Location: Install each unit level and accurately in position indicated in relation to other<br />

work; and maintain sufficient clearance for normal service and maintenance, but in no<br />

case less than that recommended by manufacturer.<br />

C. Duct Connections: Connect ductwork to air terminals in accordance with Division 23<br />

ductwork sections.<br />

1. Provide conical taps at medium-pressure branch duct takeoffs from main trunk<br />

duct to terminal units.<br />

2. Arrange medium-pressure branch ducts and takeoffs so that there are no more<br />

than two elbows or bends up to 90 degrees in branch duct to terminal unit inlets;<br />

“U” bends will not be allowed.<br />

3. Inlet branch ducts greater than 20 feet in length shall be increased in size to one<br />

full duct size larger than the terminal inlets to which they are connected. Locate<br />

reducer 3 feet ahead of terminal inlet.<br />

4. Inlet branch ducts shall have a minimum of 3 feet of straight duct ahead of the<br />

unit inlet, including no reducers.<br />

5. Medium-pressure flexible ductwork (with flexible aluminum core), when used, and<br />

where allowed by local Code, shall be limited to a maximum of 6 feet per inlet.<br />

6. Provide a minimum of 4 feet of lined low-pressure ductwork between the terminal<br />

unit outlet and the first spin-in fitting or supply air outlet branch duct takeoff.<br />

D. For fan-powered terminals, provide plenum air inlet sound attenuating boot, as indicated<br />

on drawings, and flexible connector at unit outlet.<br />

3.04 FIELD QUALITY CONTROL:<br />

A. Upon completion of installation and prior to initial operation, test and demonstrate that air<br />

terminals, and duct connections to air terminals, are leak-tight.<br />

B. Repair or replace air terminals and duct connections as required to eliminate leaks, and<br />

retest to demonstrate compliance.<br />

3.05 CLEANING:<br />

A. Clean exposed factory-finished surfaces. Repair any marred or scratched surfaces with<br />

manufacturer’s touch-up paint.<br />

3.06 BALANCING:<br />

A. See Section 230593. Balancing contractor shall set all air quantity limits, and shall not<br />

rely on any factory calibration. Report air quantity as measured by the air terminal’s<br />

velocity pressure pickup, in addition to pitot traverses and outlet readings.<br />

Project No.: 10145<br />

550 15 th Street Dual Brand Hotel<br />

03/16/2012<br />

END OF SECTION 23 3600<br />

23 3600 - 5 AIR TERMINAL UNITS