3.11 COMMISSIONING:<br />

4. Introduce chlorination material into lines and distribution system in manner<br />

approved by the Architect/ Engineer.<br />

5. After a contact period of not less than 24 hours, during which period chlorine<br />

residual shall be maintained at not less than five parts per million, flush out<br />

systems with clean water until residual content is not greater than 0.2 parts per<br />

million.<br />

6. Flush entire system, including all hose bibs, fixture outlets, dead ends, and other<br />

points where stagnant water may collect.<br />

7. Open and close valves in lines being sterilized several times during contact period.<br />

8. Furnish a copy of test report of complete and adequate sterilization to the<br />

Architect/Engineer before final acceptance of work. Certificates shall bear<br />

signature of an official of laboratory responsible for test.<br />

A. Fill system and perform initial chemical treatment.<br />

B. Check expansion tanks to determine that they are not air bound and that the system is<br />

completely full of water.<br />

C. Before operating the system, perform the following steps:<br />

1. Open valves to full open position. Close heat exchanger bypass valves.<br />

2. Remove and clean strainers.<br />

3. Check pump for proper rotation and proper wiring.<br />

4. Set automatic fill valves for required system pressure.<br />

5. Check air vents at high points of systems and determine if all are installed and<br />

operating freely (automatic type) or able to bleed air completely (manual type).<br />

6. Check operation of automatic bypass valve.<br />

7. Check and set operating temperatures of water heaters to design requirements.<br />

8. Lubricate motors and bearings.<br />

Project No.: 10145<br />

550 15 th Street Dual Brand Hotel<br />

12/23/2011<br />

END OF SECTION 22 1116<br />

22 1116 - 18 BASIC PLUMBING PIPING