1. Preliminary Testing and Balancing Schedule:<br />

Project No.: 10145<br />

550 15 th Street Dual Brand Hotel<br />

03/16/2012<br />

a. Prepare a project schedule. Schedule shall indicate critical path of the<br />

balancing process and shall incorporate both requirements of other<br />

contractors (including joint efforts) necessary to meet test and balance<br />

commitments and process flow of test and balance work. Coordinate with<br />

GC and insert critical steps into project master schedule.<br />

2. Data to be Procured:<br />

a. Fan and pump curves, including performance data.<br />

b. Manufacturer's performance data for all equipment to be balanced: Data<br />

shall include air and hydronic pressure differences, the direction of air<br />

and water flow, temperature differentials, capacities, operating<br />

temperatures and pressures, and limit of safety temperatures and<br />

pressures.<br />

c. Fan and pump motor nameplate data.<br />

d. Motor starters, including sizes, locations and thermal overload protection<br />

ratings.<br />

e. Drives: Sheave data, pitch diameters, belt sizes and quantities, limits of<br />

adjustment, types of belt guards, etc.<br />

f. Effective areas (K factors) for all air terminal devices for the velocitymeasuring<br />

instrument recommended. Also obtain air pattern adjustment<br />

and sound data.<br />

g. Manufacturer's data and test procedures for all air handling devices, such<br />

as variable air volume boxes, constant volume regulators, static pressure<br />

dampers, etc.<br />

h. Manufacturer's data for air pressure drop across louvers, filter banks,<br />

sound traps, remote coils and other devices in the air distribution system.<br />

Note whether louvers are provided with screening and whether filter<br />

pressure drop data is for clean, partially dirty, or dirty filters.<br />

i. Temperature Control Diagrams: Obtain necessary data required for TAB<br />

work.<br />

j. Assemble manufacturer's catalog data for all HVAC equipment, including<br />

pumps, air moving equipment and air terminal devices. This requirement<br />

is in addition to shop drawings and submittal data where possible. Only<br />

include performance data which pertains to the T&B work. <strong>Construction</strong><br />

technical data is not required.<br />

k. All data shall be compared to the information on the construction<br />

documents. Discrepancies shall be identified for review by the Engineer.<br />

All data shall be recorded in the design columns of NEBB report forms.<br />

3. System Schematic Drawings:<br />

a. Submit reduced drawings of each HVAC duct system. The test and<br />

balance contractor can obtain drawing files from MDP& Associates for<br />

development of these drawings.<br />

b. Submit similar drawings for extensive piping systems.<br />

c. For large buildings or where there is more than one system, submit a<br />

separate layout for each floor or for each system. Identify test locations,<br />

outlets, etc. on these drawings.<br />

d. All test locations, which include dampers, regulating devices, terminal<br />

units, supply outlets, return and exhaust inlets, etc., shall be numbered.<br />

23 0593 - 5 TESTING, ADJUSTING, AND<br />

BALANCING FOR HVAC