A. Upon completion of installation of air handling equipment, and after motor has been<br />

energized with normal power source, test equipment to demonstrate compliance with<br />

requirements. Where possible, field correct malfunctioning equipment, then retest to<br />

demonstrate compliance. Replace equipment which cannot be satisfactorily corrected.<br />

B. Manufacturer's Field Inspection: Arrange and pay f or a factory- authorized service<br />

representative to perform the following:<br />

1. Inspect the field assembly of components and installation of fans including ductwork<br />

and electrical connections.<br />

2. Prepare a written report on findings and recommended corrective actions.<br />

3.05 ADJUSTING, CLEANING, AND PROTECTING:<br />

A. Startup, test and adjust air handling equipment in presence of manufacturer's authorized<br />

representative.<br />

B. Adjust damper linkages for proper damper operation.<br />

C. Clean unit cabinet interiors to remove foreign material and construction dirt and dust.<br />

Vacuum clean fan wheel and cabinet.<br />

3.06 SPARE PARTS:<br />

A. General: Furnish to Owner with receipt one spare set of belts for each belt driven air handling<br />

equipment.<br />

3.07 COMMISSIONING:<br />

A. Final Checks Before Start-Up: Perform the following operations and checks before start-up:<br />

1. Remove shipping blocking and bracing.<br />

2. Verify unit is secure on mountings and supporting devices and that connections for<br />

piping, ductwork, and electrical are complete. Verify proper thermal overload<br />

protection is installed in motors, starters, and disconnects.<br />

3. Perform cleaning and adjusting specified in this Section.<br />

4. Disconnect fan drive from motor, verify proper motor rotation direction, and verify fan<br />

wheel free rotation and smooth bearings operations. Reconnect fan drive system,<br />

align belts, and install belt guards.<br />

5. Lubricate bearings, pulleys, belts, and other moving parts with factory-recommended<br />

lubricants.<br />

6. Verify manual and automatic volume control and that fire and smoke dampers in<br />

connected ductwork systems are in the full-open position.<br />

7. Disable automatic temperature control operators.<br />

B. Starting procedures for fans:<br />

1. Energize motor; verify proper operation of motor, drive system, and fan wheel.<br />

Adjust fan to indicated RPM.<br />

2. Replace fan and motor pulleys as required to achieve design conditions.<br />

3. Measure and record motor electrical values for voltage and amperage.<br />

Project No.: 10145<br />

550 15 th Street Dual Brand Hotel<br />

03/16/2012<br />

23 3413 - 10 HVAC FANS