05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>The</strong> <strong>Nimrod</strong> <strong>Review</strong><br />

6.6<br />

110<br />

this intake, it may be necessary either to switch off the tail pack before commencing an<br />

air-to-air refuel, or to carry out a modification on the blow-off valve outlets of Tanks 1<br />

and 6 to prevent the fuel running down the skin. 5 ’ (emphasis added).<br />

This report was distributed to 11 addressees (10 BAE Systems staff, and the MOD’s representative on site –<br />

the Resident Technical Officer (RTO)). However, the report’s distribution list does not indicate who, if anyone,<br />

was supposed to take forward the recommendations, and no evidence has been found that further work was<br />

undertaken on the threat presented by fuel entering ports and intakes after blow-off.<br />

6.7 In May 1985 British Aerospace issued a Report entitled: “NIMROD AEW3 MK 3 TESTING AND ASSESSMENT<br />

OF AIR TO AIR REFUELLING SYSTEM”, 6 which summarised a number of ground and air tests of the AEW3 AAR<br />

system. <strong>The</strong> Report also referred to the report discussed above, which it said stated:<br />

“4.1 <strong>The</strong> report also concluded that there may be some hazard from residual fuel running<br />

down the fuselage following a blow-off from Tanks 1 or 7, which should be the subject<br />

of further investigation.” 7 (emphasis added)<br />

6.8 In July 1985 British Aerospace issued a Report entitled: “NIMROD AEW3 MK 3 OPERATING INSTRUCTIONS FOR<br />

AIR TO AIR REFUELLING”. 8 <strong>The</strong> report set out operating instructions for the AEW3 during AAR, but made a<br />

number of points relevant to AAR operations generally:<br />

6.9<br />

“3.7.3. During the refuel operation, it is recommended that a look-out is kept through<br />

the escape hatch windows for fuel venting, in which case the blow-off valves of Tanks 1<br />

and 7 may have discharged fuel. If venting is seen, and Tanks 1 and 7 are full, refuelling<br />

should be discontinued. (see also paragraph 3.13).” 9 (emphasis added)<br />

“3.13. After landing. WARNING If fuel spillage has taken place in flight due to venting or<br />

to a probe mishap, do not run the APU until the APU has been inspected and declared<br />

clear of fuel.” This highlights continuing concern about fuel entering ‘ports and intakes’<br />

and reinforces that fuel entering fuselage panels was a possibility, even though the APU<br />

external panel lies flush with the fuselage.<br />

<strong>The</strong>se reports show that blow-off during AAR was recognised as a potential hazard. Although the potential<br />

hazard of No. 5 tank blow-off on the port side was dealt with, the hazard from the blow-off from No. 1 tank<br />

on the starboard side (and Nos. 6 and 7 tanks) was not. <strong>The</strong> threat of fuel entering the fuselage compartments<br />

was raised, but there is no evidence that it was ever investigated further. It is surprising that there is no record<br />

of any decision process which may have curtailed further work on these reports, particularly in view of the clear<br />

implications for flight safety.<br />

1987: Changes to Refuelling Sequence<br />

6.10<br />

6.11<br />

10 In a letter dated 15 January 1987, BAE Systems advised the RAF that the extant sequence of refuelling<br />

could potentially cause structural problems because of wing bending relief. Following trials, the sequence was<br />

changed, such that rather than filling all tanks simultaneously, the wing tanks were refuelled first, followed by<br />

the fuselage tanks, once the wing tanks were full.<br />

It is important to note that this had the incidental effect of increasing the instantaneous flow rate at which<br />

individual tanks were refuelled; the significance of this is explained later when the operation of the blow-off<br />

valve is discussed.<br />

5 Ibid, page 6.<br />

6 HAS MPP F AEW 0065 (BOI Report, Exhibit 6).<br />

7 <strong>The</strong> reference to No. 7 tank may been error as the earlier report talked of Nos. 1 and 6 tanks.<br />

8 HAS MPP F AEW 0068 (BOI Report, Exhibit 58).<br />

9 This may be a perpetuation of the previous report’s error in substituting No. 7 tank for No. 6 tank.<br />

10 JNG/CSN, dated 15 January 1987.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!