05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>The</strong> <strong>Nimrod</strong> <strong>Review</strong><br />

50<br />

Shrouds<br />

4.32<br />

be reached with high power settings). 41 <strong>The</strong> chance of fuel actually reaching and remaining on this potential<br />

point of ignition in sufficient quantity to cause a fire is, however, relatively low. During a test to determine the<br />

potential leak paths for fuel, should it leak from the aircraft vent system couplings above the unlagged bellows,<br />

none touched the bellows. 42 This was, of course, a static test and could not reproduce the variations in pitch<br />

and bank that would occur during flight. <strong>The</strong>re is no doubt though, from the information calculated by RAE<br />

and subsequently utilised by BAE Systems, that the unlagged bellows could reach the AIT for AVTUR and,<br />

therefore, by BAE Systems’ own criteria, should have been lagged. As discussed below, however, the addition of<br />

an insulation muff or shroud could have exacerbated the risk of fire in the event of leaking fuel making contact<br />

with the bellows. Whether or not the risk was properly considered at the <strong>Nimrod</strong> ‘acceptance conference’<br />

during August 1968 is a moot point (see further below).<br />

<strong>The</strong>re are two metal shrouds covering the Cross-Feed expansion bellows in the fuselage centre section; these<br />

shrouds appear to be the device used within the MR1/R1 design to insulate expansion bellows. <strong>The</strong>y consist of<br />

two half-shells, each comprising two layers of stainless steel, separated by a layer of insulation. One of these<br />

shrouds was involved in the (fortunately short-lived) fire discovered on <strong>Nimrod</strong> XV249 on 28 January 2008. An<br />

accelerant43 had entered the shroud (thus it is clearly not liquid-proof) and been ignited; the ignition process was<br />

complex, but it is believed that fuel soaked into a Cross-Feed duct mounting block, ignited and in turn ignited<br />

fumes emitting from the fluid in the shroud. 44 <strong>The</strong> investigation suggested that the accelerant had pooled within<br />

the shroud because it had been closed such that the join between its two halves was in a horizontal alignment; it<br />

was postulated that, if the shroud had been rotated through 90 degrees, the accelerant would have drained out<br />

between the join. However, prior to this incident, there was no requirement to fit the shrouds in this manner and<br />

no indication that not doing so could prove a fire hazard; furthermore, there are no drain holes in the shroud<br />

to allow drainage.<br />

Laced flexible muffs<br />

4.33<br />

4.34<br />

During the conversion process from MR1 to MR2, the addition of the SCP also brought with it the need to<br />

insulate the new duct from the surrounding structure, including the external fairing aft of the No. 7 Tank Dry<br />

Bay. <strong>The</strong> majority of the insulation on the SCP pipe is Refrasil but the expansion joints were covered by flexible<br />

muffs laced up with wire along a longitudinal seam (see Figure 4.8 below). <strong>The</strong> selection of the laced muff was<br />

driven by the need to minimise its surface area to allow it to fit into the cramped confines of the (new) SCP<br />

fairing. 45 Produced initially by Bestobell, the specification of these muffs describes the end finishing as “draw<br />

wire or cord in the hem”, “to prevent the ingress of fluid” and that “all external unproofed stitching or cloth<br />

is sealed against fluid contamination”. <strong>The</strong> muffs are faced with a metallic lacquer, which provides resistance<br />

against absorption. BAE Systems’ understanding was that these muffs would provide a liquid-proof barrier. In<br />

a BAE Systems document discussing the need to remove or replace some of the muffs, which had asbestos<br />

content, a Chapter is entitled: ‘Lagging and Insulation Muffs Design Philosophy.’ 46 This Chapter notes that: “If<br />

flammable liquids were not contained and drained, then the hot ducts would require lagging to bring surface<br />

temperatures below the ignition point of any possible leaking flammable fluids or vapours. <strong>The</strong> latter design<br />

philosophy applies in the APU and pannier bays on the <strong>Nimrod</strong> aircraft”. 47<br />

In an obvious contradiction of the design philosophy expressed above, the muff immediately aft of the SCP<br />

elbow is not long enough both to cover the exposed section of duct and to fit over the end of the Refrasil, to<br />

form a liquid tight seal (see Figure 4.8 below). In any event, the rear end of the muff abuts against a clamp<br />

which is not insulated. Moreover, the movement of the expansion bellows relative to the aircraft will always<br />

41 BOI Report, paragrapth 42(c) [2-38].<br />

42 NAEDIT/1505/09/14/Task, dated 1 September 2009.<br />

43 <strong>The</strong> investigation was unable to determine whether the accelerant was aviation fuel or hydraulic fluid.<br />

44 QinetiQ report /08/01561/5.0 dated 29 January 2009. An additional report is being compiled but was not available at time of publication of the<br />

<strong>Review</strong>.<br />

45 Evidence from Martin Breakell of BAE Systems, May 2009.<br />

46 Report MBU-DES-R-NIM-210565 dated September 2003 “Removal of Asbestos Insulation Muffs in the APU Bay PDS Task 16-3381”, page 3.<br />

47 Report MBU-DES-R-NIM-210565 dated September 2003 “Removal of Asbestos Insulation Muffs in the APU Bay PDS Task 16-3381”, page 3.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!