05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Chapter 10A – <strong>Nimrod</strong> Safety Case: <strong>The</strong> Facts (Phases 1 and 2)<br />

completed on time.” Chris Lowe’s PowerPoint presentation, in fact, put the matter even more optimistically:<br />

“Project considered to be progressing well…. BAE Systems highly confident that they will produce the Baseline<br />

Reports as programmed (end July 2004)”. It is difficult to see how this statement could properly have been<br />

made (see further below).<br />

10A.132 <strong>The</strong> minutes also record a decision that Nim(ES)Safety would arrange a meeting between BAE Systems and<br />

QinetiQ “to ensure that the SC is independently assessed without any surprises”. This was followed up by an<br />

e-mail from Frank Walsh to Martyn Mahy on 21 May 2004 in which he said: “I feel that we need a meeting<br />

between yourself, BAE Systems and me to look at the Baseline Safety Case as it develops further. That way<br />

there should be no surprises when you assess the final version.” He asked Martyn Mahy if he would make<br />

himself available for a meeting at BAE Systems’ offices at Chadderton on 17 June 2004. A meeting duly<br />

took place on that date (see further below). Martyn Mahy suggested in evidence to the <strong>Review</strong> that the<br />

minutes and e-mail somehow had different meanings and it was not contemplated at this stage that QinetiQ<br />

would “independently assess” the NSC when completed. I disagree. Martyn Mahy said in interview that he<br />

had specifically advised the IPT that: there was “there was a need for the safety case to be independently<br />

assessed or assessed by an independent body” because “Frank Walsh didn’t seem to be aware that that was<br />

a requirement.” I have found no independent evidence to support this assertion; nor is it recorded anywhere<br />

in writing, as it should have been since it represented material professional advice. In these circumstances,<br />

I do not accept that any such advice was specifically given by Martyn Mahy to Frank Walsh. As I explain<br />

in Chapter 11, however, both were, or should have been, well aware that the NSC should have been<br />

independently assessed by a properly appointed ISA.<br />

21 May 2004: BAE Systems Newsletter<br />

10A.133 In keeping with the optimistic impression he had conveyed at the Fifth PSWG, Chris Lowe submitted the<br />

following piece which was published in the internal BAE Systems’ TTRO “Weekly News” for the week ending<br />

21 May 2004:<br />

“<strong>Nimrod</strong> Platform Safety Working Group – was attended by TTRO Airworthiness at RAF<br />

Brampton on 18 May 2004. A major agenda item was a presentation of progress on the<br />

<strong>Nimrod</strong> Aircraft Level Baseline Safety Case. Whilst the group was satisfied with progress so<br />

far, there is still a high volume of work to be discharged by TTRO engineering in order to<br />

deliver the Baseline reports for approval by the end July this year and official IPT acceptance<br />

by September latest. It was pointed out that this is looked upon as a <strong>Nimrod</strong> IPT showcase<br />

project, and a fundamental milestone in <strong>Nimrod</strong> IPT 2004 activities. In view of this, Group<br />

Captain Baber wished that achievement of the Safety Case acceptance and sign-off be<br />

formally recognised by a publicity gathering to mark the occasion.” (emphasis added)<br />

10A.134 Witness K [BAE Systems]’s reaction at the time when he read this article was one of incredulity. <strong>The</strong> following<br />

entry that he made in his personal notebook (the first part of which was written in red ink for emphasis) is<br />

worth quoting in full:<br />

“Q: N.S.W.G. Major agenda item! Presentation of progress on NSC…<br />

“Group satisfied with progress so far” – what was presented? 18/05/04<br />

“Approval by end July this year” – engineering reports.<br />

Show case / milestone proj / Public gathering!<br />

<br />

engineering (and should have been supplied to program by end Feb) (final ones<br />

28off delivered 21-5-04)<br />

<br />

<br />

1 month)<br />

<br />

finish by July?”<br />

219

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!