05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Chapter 11 – <strong>Nimrod</strong> Safety Case: Analysis and Criticisms<br />

none of the hazards was really a problem and, in so far as ‘further work’ was said to be required, this was<br />

essentially BAE Systems looking for excuses to do further unnecessary work. Fourth, the general malaise that the<br />

<strong>Nimrod</strong> fleet was ‘safe anyway’ and, therefore, the NSC was merely a ‘tick-box’ paperwork exercise.<br />

(8) <strong>The</strong> <strong>Nimrod</strong> IPT failed to follow its own Safety Management Plan.<br />

11.234 In my judgement, the <strong>Nimrod</strong> IPT failed to follow its own Safety Management System (SMS). <strong>The</strong> IPT’s safety<br />

system was rightly described by Frank Walsh himself in evidence to the <strong>Review</strong> as having “broke”.<br />

SMP three-stage process<br />

11.235 George Baber, Michael Eagles and Frank Walsh all ignored, or short-circuited, the <strong>Nimrod</strong> Safety Management<br />

Plan (SMP) processes. <strong>The</strong> <strong>Nimrod</strong> IPT should have followed the three-stage “Hazard Management Process”<br />

laid down in Annex A-1 of the SMP119 to sentence all hazards identified and raised by BAES but left ‘open’. 120<br />

This was initially averred by George Baber in his written evidence, 121 and accepted by Michael Eagles and Frank<br />

Walsh and other witnesses. But when it was pointed out that the procedure had not been followed, George<br />

Baber, Michael Eagles and Frank Walsh sought to suggest that the SMP procedure did not in fact apply to the<br />

initial population of CASSANDRA. <strong>The</strong>re was, however, no other procedure could be said to apply or be relevant.<br />

In these circumstances, I am satisfied that the Annex A-1 process should have been followed. Michael Eagles<br />

accepted that Annex A-1 of the SMP was ‘the only show in town’ so far as relevant procedures for handling the<br />

NSC were concerned.<br />

By-passed<br />

11.236 Regrettably, the <strong>Nimrod</strong> IPT essentially by-passed or ignored the “Hazard Management Process” in the SMP.<br />

<strong>The</strong> SMP required an initial ‘proposed’ risk categorisation to be carried out by the appropriate LOD: however,<br />

the ‘proposed’ risk categorisation was not carried out by the appropriate LOD holder (Michael Eagles) but was<br />

carried out by Frank Walsh, who was not an LOD holder. <strong>The</strong> SMP required advice to be taken from the relevant<br />

Engineering Heads of Branch (HOB): however, in relation to the vast majority of hazards (including Hazard H73),<br />

no advice whatsoever was taken (by Frank Walsh) from relevant Engineer HOB. <strong>The</strong> SMP required all ‘A’ and ‘B’<br />

and borderline ‘C’ risk categorisations to be reviewed by the meetings of the Aircraft Safety <strong>Review</strong>s (ASR) and<br />

PSWG: however, at no stage were the vast majority of the hazards left open by BAE Systems (including Hazard<br />

H73) even considered by the ASR or the PSWG, let alone reviewed. <strong>The</strong> key role of the PSWG was recognised<br />

early on. At the Inaugural PSWG meeting on 18 March 2002, Witness C [BAE Systems] said that if the IPT did<br />

not want to task BAE Systems to sentence a risk “the hazard will go to the PSWG” and IPTL ultimately has the<br />

say whether he accepts the risk. <strong>The</strong> function of the PSWG was “to examine and sentence hazards across both<br />

marks at platform level.”<br />

11.237 <strong>The</strong>se were by no means the only respects in which the SMP was ignored. In particular, as explained above,<br />

despite having “ownership” of the NSC, Michael Eagles played little or no role in its development, either directly<br />

or indirectly, and had little direct contact with BAE Systems. Instead, he left the task almost entirely to Frank<br />

Walsh, exercising minimal supervision of his actions. Frank Walsh, for his part, failed to voice any objection to<br />

this and further failed to document the hazard identification process as required by the SMP. 122<br />

11.238 I am confident that, if it had followed the SMP, the <strong>Nimrod</strong> IPT would have picked up the fundamental mistake<br />

in Frank Walsh’s Annex A relating to the presence of a fire detection and suppression system in so many zones<br />

of the aircraft, including Zone 614. It may also have been that the discovery of this egregious mistake would<br />

have led to greater challenge to the project as a whole, and a fundamental re-examination by the <strong>Nimrod</strong> IPT<br />

of the work that BAE Systems had done. I am bound to say, however, that I am not sanguine that this would,<br />

ultimately, have led to a different outcome because of the general lassitude and lack of real interest in the<br />

content of NSC by those involved.<br />

119 Set out in Chapter 9 at paragraph 9.77.<br />

120 Ibid, paragraph 15, page C-5, provided that hazard identification could come from any source, e.g. individual IPT members, industry or users.<br />

121 Although George Baber somewhat equivocated in his oral evidence when it was pointed out that the process had not been followed.<br />

122 Ibid, paragraph 14.<br />

317

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!