05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

7.25<br />

Chapter 7 – Damage from Cross-Feed/SCP Duct Failure<br />

In February 2005, BAE Systems published its Feasibility Study into the Introduction of a Bleed Air Leak Detection<br />

System. 34 <strong>The</strong> study recommended a system which could be used both to detect leaks and automatically shut<br />

down the cross-bleed air. <strong>The</strong> study also noted that the flow-limiting venturi, used to detect air leaks in the SCP<br />

duct downstream of the duct that failed on XV227, would only detect leaks above a certain threshold level “thus<br />

a high magnitude of leaking airflow would exist undetected” 35 . <strong>The</strong> ten page document was, however, a highlevel<br />

feasibility study and noted that “the current main concern...rests with the detailed design solution further<br />

required to achieve a fully workable system”. As discussed further below, the <strong>Nimrod</strong> IPT was in due course to<br />

decide against fitting such a system, on the grounds that to do so was “not practical [when] factored against<br />

the MR Mk2 OSD”. 36<br />

7.26 On 3 March 2005, pursuant to PDS Task 16-3491, BAE Systems sent to the <strong>Nimrod</strong> IPT its “Provisions of Repair/<br />

Recovery Advice” in relation to the failure of the SCP duct on XV227. 37 <strong>The</strong> work undertaken by BAE Systems<br />

in this respect included an investigation into the residual strength of the lower rear spar in the area adjacent to<br />

the failed duct which had been affected by heat. This was found to have been reduced by approximately 25%.<br />

(In the event, the damage to the aircraft was so severe that it was deemed to be incapable of repair and XV227<br />

was cleared for one flight only, in benign weather conditions, to join the MRA4 conversion programme). BAE<br />

Systems’ advice of 3 March 2005 also referred to the fact that seals removed from pipe couplings adjacent to the<br />

duct failure were found to have suffered significant deterioration, stating that it was “strongly suspected that<br />

the deterioration of the polysulphide seal material has been caused by exposure to excessive temperatures”.<br />

<strong>The</strong> decision to switch back on the SCP<br />

7.27<br />

In view of the corrosion detected on the duct that failed on XV227, the IPT decided that that particular duct<br />

should be replaced on all <strong>Nimrod</strong> MR2s. On 26 April 2005, the <strong>Nimrod</strong> IPT issued a Routine Technical Instruction<br />

(RTI) which permitted the SCP to be switched back on, and used in flight, once the relevant bellows section of<br />

SCP ducting had been replaced, which work had to be carried out at the first suitable maintenance opportunity<br />

after receipt of the replacement duct. 38 Pursuant to this Instruction, the replacement of the relevant section of<br />

ducting duly took place on the MR2 fleet between April 2005 and April 2006. 39<br />

Rationale of the <strong>Nimrod</strong> IPT’s decision to switch back on the SCP<br />

7.28<br />

<strong>The</strong> IPT’s decision to allow the use of the SCP following the XV227 incident was based on its belief that all hot air<br />

leaks (with the exception of any from the SCP bellows that had failed on XV227 and which were to be replaced)<br />

would be detected by the aircraft’s overheat detection system or other warning system (see further below). As<br />

the SCP bellows had been replaced and, as the only example of that duct to fail (XV227’s) was over 20 years<br />

old when it fractured, it was felt that there was a minimal risk of the same duct failing again. <strong>The</strong> logic of this<br />

line of argument meant that the IPT could consider resuming use of the SCP before receiving the results of BAE<br />

Systems’ further work into corrosion in other elements of the hot air system: even if a duct failed it would be<br />

detected, enabling the crew to shut the system down before damage was caused to the aircraft. <strong>The</strong> IPT had<br />

sought clarification from BAE Systems as to the capability of the hot air leak detection systems, but were told<br />

“we are unable to comment on the capability of the existing system to detect such leaks without further study<br />

and tasking.” 40 This would appear to demonstrate either: (a) a surprising lack of knowledge of the capabilities<br />

of ‘as designed’ systems by the aircraft designer itself; or (b) a marked reluctance to disclose important, safety<br />

related design information without being formally tasked and paid. In seeking clarification, the IPT was obviously<br />

considering the possibility of the existing hot air warning system not having comprehensive coverage. It seems<br />

it then decided to go ahead and undertake its own assessment of the position.<br />

34 Report No. MBU-DES-R-NIM-210758. dated February 2005.<br />

35 Ibid.<br />

36 Out-of-Service Date.<br />

37 RJO-NIM-05-003.<br />

38 RTI/NIM/119, dated 23 April 2005; Nim(ES)Av(A).<br />

39 <strong>The</strong> relevant section of ducting was replaced on XV230 on 4 July 2005.<br />

40 E-mail dated 19 January 2005, titled “RE:Task 16-3468”, from BAE Systems and <strong>Nimrod</strong> IPT.<br />

139

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!