05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>The</strong> <strong>Nimrod</strong> <strong>Review</strong><br />

10B.36 I deal in Chapter 11 with the appropriateness of QinetiQ’s conduct in supporting the sign-off of the BLSC.<br />

I conclude that it was manifestly inappropriate, not least because QinetiQ had neither read the Reports, nor<br />

checked them, nor seen any ISA review. Furthermore, the BLSC contained large holes: 40% of the hazards<br />

remained “Open” and 30% “Unclassified” with a series of open-ended recommendations.<br />

Sentencing of remaining hazards by the <strong>Nimrod</strong> IPT<br />

10B.37 I now turn to how the remaining “Open” and “Unclassified” hazards came to be sentenced by the <strong>Nimrod</strong> IPT<br />

such that, by March 2005, the NSC was considered completed and proof that both <strong>Nimrod</strong> types were ALARP.<br />

Irony<br />

10B.38<br />

248<br />

<strong>The</strong>re is an irony about these events. BAE Systems had failed to complete the BLSC by a substantial margin,<br />

having left a large proportion of hazards “Open” and “Unclassified” (including Hazard H73 which it had<br />

failed to analyse properly in the first place). BAE Systems sought, effectively, to pass a substantial proportion<br />

of the NSC task back to the <strong>Nimrod</strong> IPT undone. This meant that, in theory at least, the <strong>Nimrod</strong> IPT had<br />

a fresh opportunity to capture the risks which BAE Systems had not previously spotted, including the risk<br />

inherent in Hazard H73. Unfortunately, the <strong>Nimrod</strong> IPT failed to grasp this opportunity. This was for a variety<br />

of reasons, but not least that the <strong>Nimrod</strong> IPT’s guard was down because of what they had understood from<br />

the Customer Acceptance Conference. This was, however, no excuse for their failure to analyse and sentence<br />

these remaining risks properly.<br />

15 December 2004: Formal ‘sign-off’ letter of the BLSC by George Baber<br />

10B.39<br />

10B.40<br />

Frank Walsh had been tasked by the Sixth PSWG meeting to produce a document for the IPTL to ‘sign off’<br />

the NSC. On 15 December 2004, he presented a memo to George Baber for signature with wide distribution<br />

(including to DG Log(Strike), D Log 2/3 Gp and AD Eng Pol) announcing the IPTL’s intention to sign-off the<br />

<strong>Nimrod</strong> BLSC. <strong>The</strong> memo said that the production of the NSC for the MR2 and the R1 had been completed by<br />

BAE Systems, and that their reports concluded that the platforms were “ACCEPTABLY SAFE TO OPERATE AND<br />

MAINTAIN UP TO RETIREMENT FROM SERVICE…” but the Reports were too large to distribute and would be<br />

kept on file. <strong>The</strong> memo concluded:<br />

“<strong>The</strong>refore, following acceptance of the Reports at the 6th <strong>Nimrod</strong> Platform Safety<br />

Working Group held on 10 Nov 04, I am pleased to advise of my intention to sign-off the<br />

<strong>Nimrod</strong> Baseline SC. I would like to thank and congratulate both BAE Systems and EWAD<br />

on the depth of detail and standard of production that they have employed in meeting the<br />

requirements of a Baseline SC.”<br />

On 22 December 2004, Frank Walsh faxed a copy of this memo to Witness C [BAE Systems] referring to it as<br />

the ‘baseline’ letter.<br />

20 January 2005: E-mail from Frank Walsh to George Baber<br />

10B.41<br />

On 20 January 2005, Frank Walsh e-mailed George Baber as follows:<br />

“George,<br />

All the hazards in CASSANDRA, with the exception of H2 .... have controls<br />

and references in place to show that they are at ALARP. I am awaiting a copy<br />

of the Unit snow and ice plan to include as mitigation for H2.<br />

I believe that the hazards, except H2, should be set to MANAGED on<br />

CASSANDRA now and H2 when the last piece of mitigation is in place.<br />

If you agree I will instruct BAE Systems to amend CASSANDRA.<br />

Frank”

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!