05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

<strong>The</strong> <strong>Nimrod</strong> <strong>Review</strong><br />

10A.167<br />

10A.168<br />

226<br />

Following the meeting, Witness K [BAE Systems] wrote a personal note to himself which showed his<br />

frustration:<br />

“[Witness K] Note (Personal)<br />

Seemed pointless to contest the end of week completion date as all know % complete is<br />

stated as 68% and we’ve been on the job for over 4 months and at best completing end<br />

date by end Aug-mid Sept. Also no metrics to size each of remaining tasks has been done.<br />

So no-one around the table had an est. of hours to completion, only hours remaining.<br />

No accurate estimate; no rate of completion figure; no calculated end date therefore no<br />

chance of an accurate forecasted completion date, obvious end of week crap but one<br />

guess I suppose is all that’s req’d. CL & RO: Sat end of week is sched finish. I suppose<br />

that we’re 2/3/4 weeks behind approach will be used in the forth-coming weeks. TTRO<br />

planning at its best!!!!!”<br />

Witness K [BAE Systems] shared his concerns with his line manager, Eric Prince.<br />

Electrical Systems merely add ‘addendum’ to completed Mech Systems Pro-Formas<br />

10A.169 In order to speed up the Electrical Systems response, on 16 August 2004, a change of approach was adopted.<br />

Rather than producing their own separate ‘stand alone’ Pro-Formas, it was decided that Electrical Systems<br />

would simply add an addendum to Mech Systems’ Pro-Formas where Electrical Systems’ input was required.<br />

This was plainly cutting corners. As will be seen, the quality of analysis by Electrical Systems deteriorated<br />

markedly as time ran short. On 17 August 2004 alone, Witness T [BAE Systems] sent by e-mail three Electrical<br />

Systems ‘addenda’ to Mech Systems for incorporation. An increasing number of addenda completed by<br />

Witness T [BAE Systems] in the latter half of August simply contained the phrase, “Further analytical techniques<br />

are considered necessary in order to categorise the risk…”. <strong>The</strong> reason for this was quite simply that Witness<br />

T [BAE Systems] ran out of time to conduct the necessary analysis, as various witnesses such as Witness C<br />

[BAE Systems] confirmed. <strong>The</strong> effect of this rider was that hazards which had been classified as ‘Improbable’<br />

or ‘Remote’ by Mech Systems became ‘Unclassified’. This was also unsatisfactory, as I discuss in more detail<br />

in Chapter 11.<br />

23 August 2004: Mech Systems Pro-forma for Hazard H73 finalised and approved<br />

10A.170 <strong>The</strong> next two weeks involved a period of frantic activity, particularly in Mech Systems and Electrical Systems,<br />

processing Pro-Formas. It fell to Witness R [BAE Systems], who had been seconded to Mech Systems, to draw<br />

up the crucial Mech Systems Zonal Hazard Analysis Pro-Forma for zones 514/614 relating to the No. 7 Tank<br />

Dry Bays (port and starboard) and the risks associated with the Cross-Feed/SCP duct. This was known as zonal<br />

Hazard H73. Witness R [BAE Systems] finalised and signed the Mech Systems Pro-Forma for Hazard H73 on<br />

23 August 2004. Eric Prince added his signature on the same day against the legend “Contents Approved”.<br />

10A.171 Zonal Hazard H73 represented the rationalisation and combining of two zonal hazards, Hazard H367 and<br />

Hazard H498:

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!