05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>The</strong> <strong>Nimrod</strong> <strong>Review</strong><br />

10A.77<br />

208<br />

<strong>The</strong> jpg photographs for hazards H367 and H498 were incorrectly labelled in the CASSANDRA log entries:<br />

photo Dcp0221.jpg related to Zone 614 (i.e. the starboard No. 7 Tank Dry Bay) not 514; and photo Dcp0312.<br />

jpg related to Zone 514 only (i.e. the port No. 7 Tank Dry Bay) not both Zones 514 and 614. This meant that<br />

a person looking at the photographs later was going to have considerable difficulty in understanding which<br />

was which, let alone appreciating that there was a significant difference between the port and starboard<br />

No. 7 Tank Dry Bays. Furthermore, the gaps in the insulation and the deterioration in the condition of<br />

the insulation are not apparent from the photographs. Indeed, both photographs give the impression that<br />

the condition of the insulation of the Cross-Feed pipe and SCP pipe was good. As I explain in Chapter 4,<br />

however, that was not the case: much of the Refrasil insulation was old and deteriorated throughout much<br />

of the <strong>Nimrod</strong> fleet.<br />

10A.78 Witness K [BAE Systems] was, therefore, right when he subsequently wrote on 7 June 2004: “Given a zone<br />

and a picture, identifying the systems at risk will be a mammoth task.” <strong>The</strong> poor quality of the initial zonal<br />

hazard reports and photos (some of which were not labelled at all and some of which it was difficult to tell<br />

whether they were up or down) was the subject of complaint subsequently by those tasked to carry out<br />

the analysis and mitigation exercise, such that Richard Oldfield was obliged to offer a further aircraft at RAF<br />

Woodford for viewing and the assistance of the BAE Systems’ Field Service Representative at RAF Kinloss at a<br />

Phase 2 progress meeting on 7 July 2004. This offer was, unfortunately, never taken up.<br />

4 March 2003: QinetiQ TRM confirms QinetiQ will ‘review’ NSC<br />

10A.79 At a QinetiQ TRM on 4 March 2003, it was noted that BAE Systems hoped to sign off the NSC “ by the end<br />

of 2003”, and it was agreed that QinetiQ “would have the opportunity to review the work done by BAE<br />

Systems”.<br />

April 2003: BAE Systems deliver Phase 1 <strong>Nimrod</strong> Baseline Safety Case Report<br />

10A.80<br />

10A.81<br />

10A.82<br />

In April 2003, BAE Systems delivered its Report on Phase 1 of the <strong>Nimrod</strong> Baseline Safety Case comprising<br />

the Zonal Hazard Analysis (ZHA) of the MR2 and R1 (BLSC (Phase 1) Reports). 51 <strong>The</strong> BLSC (Phase 1) Report for<br />

the MR2 identified some 1,300 hazards. As explained later, this enormous number of ‘hazards’ is indicative<br />

of a lack of understanding by BAE Systems at the time as to what comprised a ‘hazard’ and what comprised<br />

an ‘event or cause’. <strong>The</strong> majority of the 1,300 initial hazards were avionic-related and repeats of each other<br />

with small variations. Many were not ‘real’ hazards in the first place as they assumed, e.g., that a pilot would<br />

only look at a single instrument erroneous indication and follow it blindly.<br />

<strong>The</strong> BLSC (Phase 1) Report annexed the CASSANDRA Hazard Log entries for Hazards H367 and H498 set<br />

out above. As explained above, these identified the general zonal risk arising from the juxtaposition of fuel<br />

pipes and hot bleed-air ducting in Zones 514 and 614 but: (i) contained little analysis or detail; (ii) did not<br />

distinguish between the port and starboard sides, and in particular, did not highlight the special risk on the<br />

starboard side arising from the SCP pipe and elbow at the bottom of Zone 614; (iii) ascribed different initial<br />

probabilities to the same zones and hazard; and (iv) cross-referred photographs that were confusing and<br />

difficult to follow. This did not bode well for any subsequent hazard analysis.<br />

In an accompanying Phase 1 ‘Completion’ Report, BAE Systems reported that it had completed Phase 1 and<br />

recommended that it be tasked to carry out Phase 2. 52<br />

1 May 2003: <strong>Nimrod</strong> IPT acceptance of completion of Phase 1<br />

10A.83<br />

By a letter dated 1 May 2003, Frank Walsh (who had joined the <strong>Nimrod</strong> IPT in January 2003 as Safety<br />

Manager) confirmed acceptance of the completion by BAE Systems of Phase 1 of the NSC and acknowledged<br />

receipt of a soft copy of the Hazard Log “populated but not mitigated”. He made arrangements for BAE<br />

Systems to be paid for Phase 1 and requested BAE Systems to prepare costings for Phase 2 of the contract<br />

“now the scope of the task is clear.”<br />

51 BAE Report MBU-DEF-C-NIM-SC0538: <strong>Nimrod</strong> MR Mk2 – Baseline Safety Case (Phase 1) Zonal Hazard Analysis (April 2003) (BLSC (Phase 1)<br />

Report).<br />

52 BAE Report MBU-DEF-C-NIM-SC0539. <strong>Nimrod</strong> Task 26-3244 Equipment Safety Management Safety Management <strong>Nimrod</strong> MR MK2 and R Mk1.<br />

Preliminary Hazard Identification Report – Phase 1 Completion (April 2003).

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!