05.04.2013 Views

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

The Nimrod Review - Official Documents

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

<strong>The</strong> <strong>Nimrod</strong> <strong>Review</strong><br />

7.29<br />

7.30<br />

7.31<br />

7.32<br />

7.33<br />

140<br />

However, the IPT’s assessment proved to be imperfect and was based on an overly optimistic understanding of<br />

the capabilities of the centre section overheat detection system. <strong>The</strong> <strong>Nimrod</strong>’s overheat detection system has 28<br />

detectors (temperature sensitive switches) that operate warning lights on the air engineer’s panel if they detect<br />

a temperature rise above a pre-set level. <strong>The</strong> detectors are connected in five groups, operating at either 150°C<br />

or 230°C depending on their installed position. One group is positioned in each Rib 2 (between each pair of<br />

engines) and one group in each wing leading edge. <strong>The</strong> remaining group forms a “centre section” overheat<br />

detection system, as described in the Aircrew Manual Book 1 (Technical). 41 However, this description is, to some<br />

extent a misnomer: this element of the system in fact consists of ten sensors in two groups either side of the<br />

aircraft fuselage. <strong>The</strong> actual locations of the sensors are: one in the No. 7 Tank Dry Bay, one just in the bomb<br />

bay (adjacent to the No. 7 Tank Dry Bay) two in Rib 1 and one in Zone 2 of the inboard engine.<br />

In view of the detection temperature of the centre section overheat sensors, it is unlikely that they would detect<br />

anything other than a leak in their close vicinity, meaning that a significant section of the Cross-Feed pipe as<br />

it traverses the bomb bay is effectively unmonitored. Further, in the case of XV227, the No. 7 Tank Dry Bay<br />

had been filled with enough hot air to cause significant and widespread damage. One of the centre section<br />

overheat system’s detectors is in that bay and yet there is no record of it being activated. Unfortunately, there is<br />

no record of whether or not this sensor was subsequently tested for serviceability. It was worth remembering,<br />

however, that in the case of XV230, the BOI recorded that the centre section overheat warning was not reported<br />

as activated by what was, without doubt, a large fire within the aircraft’s starboard No. 7 Tank Dry Bay, the<br />

heat from which reached into the bomb bay. <strong>The</strong> BOI did note that there could be two explanations for this:<br />

(1) the electrical power to the system could have been disrupted by the fire before it could register the rise in<br />

temperature; or (2) another possibility was that the centre section overheat was triggered at about the same time<br />

as the other alarms, but the air engineer chose not to mention it on intercom as it was, by then, superfluous. 42<br />

<strong>The</strong>re is nonetheless, in my view, sufficient evidence to conclude that the centre section overheat sensors would<br />

not necessarily detect a leak in the Cross-Feed pipe as it traverses the bomb bay.<br />

This was, of course, a weakness that had existed in the aircraft since its inception, but a more detailed analysis<br />

should have picked it up. Indeed, the XV227 UI had noted this weakness: “there is no hot air leak warning<br />

system for the ruptured duct or the cross-bleed air duct as it passes through the bomb bay”. One of the<br />

UI’s recommendations was that a leak-detection capability should be fitted for the “ruptured duct and crossair<br />

bleed ducts” (emphasis added), although this was subsequently rejected as it could not be fitted in the<br />

remaining life of the aircraft. <strong>The</strong> UI report was published in July 2005, some two to three months after the<br />

decision was taken to switch the SCP back on in April 2005. As noted above, the BAE Systems study into a<br />

leak detection system had also identified a weakness in the current warning system, i.e. that the venturi/under<br />

pressure warning system would only detect relatively large leaks. However, at no stage does anyone appear to<br />

have attempted to reconcile the conflicting views of the IPT, BAE Systems and the UI over the efficacy of the<br />

aircraft’s hot air leak detection system.<br />

It was suggested at the Inquest by Air Commodore George Baber that the decision to allow the SCP to be<br />

switched back on was not simply an engineering decision, but was further influenced by pressure from the<br />

aircrew community: “And in conjunction with discussions with our operating crews, and it wasn’t just a sole IPT<br />

decision, this was done in conjunction with the operating crews, the decision was made that this was a sensible<br />

thing to do”. 43<br />

Whilst a number of <strong>Nimrod</strong> IPT witnesses confirmed to the <strong>Review</strong> that the operator community was keen<br />

to regain the use of the SCP (particularly as summer approached in the Gulf), there is no evidence to suggest<br />

that the decision to switch the SCP back on after the XV227 incident was improperly affected by operational<br />

pressures. On the contrary, the aircrew at RAF Kinloss relied on the engineering judgment of the IPT to provide<br />

them with an aircraft that was safe to operate.<br />

41 AP101B-0503-15A, Part 2, Chapter 8.<br />

42 With a bomb bay fire alarm, an underfloor warning activated and reports of smoke coming from two underfloor bays, reporting the centre section<br />

overheat would have added nothing to the crew’s understanding of the situation.<br />

43 Inquest transcript, 13 May 2008, page 227.

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!